InvestorsHub Logo

1vman

03/04/18 2:09 PM

#279493 RE: frontloading #279449

*****Front , I don't see no CofO issued yet for AGs grow op !!!

What I do see however are several electrical issues and a few others that need to be addressed yet according to the building inspectors - quite a few actually in the last inspection note on 2/22/18

So with all that work still needing to be completed then inspected I don't see any way AG meets the next deadline of "No Later Than End Of March" - which was stated in their financial information statement



https://apps-secure.phoenix.gov/PDD/Search/Permits