InvestorsHub Logo

gitreal

03/27/17 11:29 PM

#14942 RE: JTrox #14940

It says leaching to begin end of February, with "production" by end of March. That suggests it takes a month - therefore, production won't happen until middle of April since leaching didn't happen until March 13th.

Yeah, I know, just minor details. Soon, the company is going to run out of room to store gold bars and all these delays and missed deadlines will be long forgotten.

rbtree

03/27/17 11:58 PM

#14943 RE: JTrox #14940

Thanks. I didn't bother going back that far, since I knew they had more delays.

Note they stated:

They also stated that cyanide leaching of the pad will begin by the end of February with production occurring by the end of March.

Well, as gitreal stated, leaching didn't start till a couple weeks ago.
So, reckon we'll have to wait to see if the claim which was made of a pour by Saturday actually happens..... it certainly wasn't stated publicly by management since they began leaching.