Should have a nice run coming to completion and production of the Sam Ramon mine .

Development and Construction of the San Ramon Gold Mine and Mill

The overall project is approximately 70% complete (based on physical completion), with earthworks, concrete, platework, steelwork and mechanical equipment installation on schedule for 100% practical completion in July 2016. Piping, electrical and instrumentation installation would continue to completion during Q3 2016.