Chipguy, This slide puts production of 65nm in Dec. Do you know if this means production start or production out?

Considering the timing with respect to verification activity
I'd say it was release to manufacturing. Add on the normal
fab cycle time, packaging, testing etc and it looks like the
65 nm parts will start flowing into the market in late Q1.

It is possible AMD will do a risk start in parallel with the
final verification and there could be some parts available
about a month earlier (Feb). It depends on much pressure
AMD is under to ship something ASAP.



imho

07/11/06 2:23 PM

#30350 RE: Ixse #30342

ixse,

This slide puts production of 65nm in Dec.

Not sure the relavence to your question, but note these are "Samples Schedule" - production 65nm in Dec.

Sorry if I am just "nitpicking",

IMHO