#18968 RE: zeynoc #18967

Thanks.....a little legalese to put you to sleep. The contracting agency can tell the awardee to proceed or not proceed, as you indicated. Depends on the nature of the complaint.

http://www.gpo.gov/fdsys/pkg/USCODE-2011-title31/html/USCODE-2011-title31-subtitleIII-chap35-subchapV-sec3553.htm

wenttocalifornia

11/28/14 1:54 PM

#19008 RE: zeynoc #18967

IMSC should sue for triple damages, IMO

b9molecule

11/28/14 3:05 PM

#19009 RE: zeynoc #18967

(c)
(1) Except as provided in paragraph (2) of this subsection, a contract may not be awarded in any procurement after the Federal agency has received notice of a protest with respect to such procurement from the Comptroller General and while the protest is pending.
(2) The head of the procuring activity responsible for award of a contract may authorize the award of the contract (notwithstanding a protest of which the Federal agency has notice under this section)—
(A) upon a written finding that urgent and compelling circumstances which significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General under this subchapter; and
(B) after the Comptroller General is advised of that finding.
(3) A finding may not be made under paragraph (2)(A) of this subsection unless the award of the contract is otherwise likely to occur within 30 days after the making of such finding.

(d)
(1) A contractor awarded a Federal agency contract may, during the period described in paragraph (4), begin performance of the contract and engage in any related activities that result in obligations being incurred by the United States under the contract unless the contracting officer responsible for the award of the contract withholds authorization to proceed with performance of the contract.
(2) The contracting officer may withhold an authorization to proceed with performance of the contract during the period described in paragraph (4) if the contracting officer determines in writing that—
(A) a protest is likely to be filed; and
(B) the immediate performance of the contract is not in the best interests of the United States.
(3)
(A) If the Federal agency awarding the contract receives notice of a protest in accordance with this section during the period described in paragraph (4)—
(i) the contracting officer may not authorize performance of the contract to begin while the protest is pending; or
(ii) if authorization for contract performance to proceed was not withheld in accordance with paragraph (2) before receipt of the notice, the contracting officer shall immediately direct the contractor to cease performance under the contract and to suspend any related activities that may result in additional obligations being incurred by the United States under that contract.
(B) Performance and related activities suspended pursuant to subparagraph (A)(ii) by reason of a protest may not be resumed while the protest is pending.
(C) The head of the procuring activity may authorize the performance of the contract (notwithstanding a protest of which the Federal agency has notice under this section)—
(i) upon a written finding that—
(I) performance of the contract is in the best interests of the United States; or
(II) urgent and compelling circumstances that significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General concerning the protest; and
(ii) after the Comptroller General is notified of that finding.
(4) The period referred to in paragraphs (2) and (3)(A), with respect to a contract, is the period beginning on the date of the contract award and ending on the later of—
(A) the date that is 10 days after the date of the contract award; or
(B) the date that is 5 days after the debriefing date offered to an unsuccessful offeror for any debriefing that is requested and, when requested, is required.
http://www.law.cornell.edu/uscode/text/31/3553#c

also, see: http://www.gao.gov/legal/bids/bibreg.html