#55963 RE: tpizzazz24 #55961

Most people think same crew does all at once but that's not how it works. You segment the work in sections. So one week one crew diggs, another lays the concrete, the next piping, and so on. This way you can do a lot more pools with minimal crews. Each segment has a specific job. Then moves on.

Forty Six & 2

06/21/14 7:59 AM

#55975 RE: tpizzazz24 #55961

Pools are built year round down here

Dallas77

06/21/14 8:45 AM

#55985 RE: tpizzazz24 #55961