Re: User336447 post# 264131

Thursday, 04/03/2014 7:06:18 AM

Thursday, April 03, 2014 7:06:18 AM

Post# of 312016
The good working relationship with the dec due to p2o's spectacularly eco friendly process is precisely why companies will choose jbii over another pyrolysis company.

Or not. Consider:



Now, how did the water get in the waste oil/HTF? Perhaps this will enlighten:


TELECON ECO JIM ROGERS - NYSDEC LAW ENFORCEMENT. ECO ROGERS INSPECTED SITE AND FOUND WHAT APPEARED TO BE STAINING FROM CUTTING OIL SPILLS AND NUMEROUS DRUMS WITHOUT TOPS AND OUTSIDE, SO RAINWATER ENTERS THE DRUMS AND CAUSES THEM TO OVERFLOW AND SPILL. THERE ARE ALSO PLASTIC TOTES INSIDE METAL CAGES THAT HE WAS TOLD ALSO CONTAINED CUTTING OIL. DURING HIS INSPECTION, JBI PERSONNEL SAID THEY'VE HAD CONTACT W/EFRAT FORGETTE - NYSDEC DIV OF MANAGED MATERIALS. THEREFORE, HE WILL CONTACT HER TO BE PART OF A JOINT INSPECTION.

5/14/13:JOINT INSPECTION SET UP FOR 5/17.

5/17/13:JIM ROGERS, SAC INSPECT SITE. MET W/AL LIBERATORE - JBI SECURITY AND RANCE HARRIS -JBI. STAINED AREAS FROM: 1)LEAKING CONTAINERS, OLD EQUIPMENT, TRANSFER OF CUTTING OIL INTO 15,000 GALLON TANKS BOTH INSIDE AND OUTSIDE THE DIKE. ALSO, DRUMS AND TOTES OF OIL, MISLABELED DRUMS AND DRUMS W/HAZARDOUS LABELS BUT WITH THE CONTENTS THAT MAY BE DIFFERENT. SAC TO FOLLOW UP W/DEC-MATERIALS MANAGEMENT AND DEC-DER/RCRA REGARDING INSPECTION.

SAC SPOKE TO DENNIS WEISS, DEC-DER/RCRA. MR. WEISS RECOMMENDED DISCUSSING SITE W/DEC INSPECTORS NEXT WEEK.

SAC SPOKE TO AES REGARDING PBS ISSUES. SHOWED HER INSPECTION PHOTOS. SHE WILL FOLLOW UP ON PBS VIOLATIONS.

5/23/13:EFRAT FORGETTE, NELSON SCHNABEL, AES, SAC INSPECT SITE. MET W/JOHN BORDYNUIK AND TOM WILSON. STAINED AREAS ON SITE HAVE BEEN REMOVED AND SOIL HAS BEEN PLACED IN PLASTIC TOTES. THEY ARE ALSO IN THE PROCESS OF CLEANING OUT THE CONTAINMENT DIKES AROUND THE TANKS. THE PRODUCT WATER MIXTURE IS BEING PUMPED BACK INTO THE TANKS.

5/31/13:SAC TELECON HAL PIERCE - ISLE CHEM. MR. PIERCE SAID CONTAMINATED SOIL WILL BE DISPOSED.

6/5/13:SAC INSPECT SITE. MET W/JOHN BORDYNUIK. CLEAN UP OF CONTAINMENT DIKES HAS NOT BEEN COMPLETED. MR. BRODYNUIK SAID IT SHOULD BE DONE BY THE MIDDLE OF NEXT WEEK.

6/12/13:SAC TELECON HAL PIERCE. MR. PIERCE REQUESTED INSPECTION. CLEAN UP HAS BEEN COMPLETED.
ARRANGED INSPECTION ON 6/14.

6/21/13:SAC INSPECT SITE. INSPECTION SCHEDULED FOR LAST WEEK HAD TO BE CANCELLED. MET W/HAL PIERCE, DANIEL RIORDAN AND JOHN BORDYNUIK. SPILL IN BOTH CONTAINMENT DIKES STILL HAVE NOT BEEN CLEAN UP SUFFICIENTLY. THEY HAVE TRIED TO USE DEGREASERS. THERE PLASTIC DIKE HAS MANY FOLDS AND IT APPEARS IT MAY NOT HAVE BEEN INSTALLED PROPERLY. THEY WILL RESEARCH AND SEND IN A LETTER FOR A SOLUTION/WORK PLAN. MR. BORDYNUIK IS LOOKING INTO POSSIBLY REPLACING DIKE W/A CONCRETE SYSTEM. CONTAMINATED SOIL THAT WAS REMOVED AND PLACED IN TOTES REMAINS ON-SITE. IT WILL BE SAMPLED FOR WASTE CHARACTERIZATION FOR DISPOSAL.

7/10/13:RECEIVED LETTER FROM DANIEL RIORDAN. JBI PLANS TO REPLACE THE CONTAINMENT SYSTEMS W/ROOF SINGLE WALL CONTAINMENT SYSTEMS AND DISPOSE OF THE FORMER SYSTEMS. THEY WILL ALSO HAVE PLANS FOR A CONCRETE CONTAINMENT LOADING AREA.

7/18/13:SAC TELECON DANIEL RIORDAN. SAC REQUESTED SCHEDULE FOR THE CONTAINMENT AREA WORK AND HOW THEY WILL ADDRESS AND DISPOSE OF THE CONTAINMENT WHERE THE SPILLS OCCURRED. MR. RIORDAN SAID HE IS NOT THE PROJECT MANAGER FOR THE WORK BUT WILL FIND OUT AND GET BACK TO SAC. HE ALSO SAID THEY HAVE BEEN STRETCHING AND SMOOTHING OUT THE CONTAINMENT PLASTIC WITHIN THE STEEL FRAME TO ALLOW BETTER ACCESS AND THEN USING A SHOP VAC TO REMOVE THE CUTTING OIL.

8/1/13:SAC TELECON DANIEL RIORDAN. MR. RIORDAN SAID HE IS SENDING A LETTER WHICH SAC SHOULD RECEIVE EARLY NEXT WEEK WITH THE SCHEDULE AND DRAWINGS FOR THE CONTAINMENT SYSTEM. THEY HAVE RECEIVED THE METAL AND WILL BE CONSTRUCTING THE CONTAINMENT WITH JBI PERSONNEL.|2013-05-20 14:30:00|2013-08-01 16:54:15.873000000|JOHN BORDYNUIK|JBI, INC.|20 IROQUOIS STREET|NIAGARA FALLS|NY|14303 |001|JOHN BORDYNUIK|(716) 251-9612||False


1302657|483100|ER|JBI INCORPORATED|438312|20 IROQUOIS ST||NIAGARA FALLS|Niagara| |3211|9|RJJONAK||2013-06-10 14:30:00|2013-06-11 16:13:00| |Human Error||Commercial/Industrial|Other|cleanup done||False||False|False|C3||1|6/11/2013: RJJ TELECON DANIEL RIORDAN,JBI INC.,HE SAID THAT ~25 GALS. OF HI-TEMP TRANSFER OIL LEAKED OUT,ALL ON THEIR CONCRETE PAD,DUE TO NOT SHUTTING OFF THE VALVE(HUMAN ERROR),BEHIND THEIR BUILDING...JBI PERSONNEL USED ABSORBANTS TO CONTAIN AND THEN CLEANED-UP ALL THE SPILL MATERIAL...HE DID SAY THAT A SMALL AMOUNT RAN OFF THE PAD ONTO SOIL,WHICH THEY ALSO SCRAPED-UP...THEY WILL DISPOSE ALL THIS MATERIAL...I LEFT A MESSAGE WITH PAUL DICKY,NCHD,EXPLAINING THIS INCIDENT & WILL FAX A COPY OF THIS SPILL IN THE MORNING TO HIM.

6/19/13:RECEIVED COMPANY INCIDENT LETTER REPORT FROM DAN RIORDAN.

6/21/13:SAC INSPECT SITE. MET W/DAN RIORDAN, HAL PIERCE, JOHN BORDYNUIK - JBI, INC. AREA OF CONCRETE WHERE THE SPILL OCCURRED WAS CLEANED UP. SMALL AMOUNT DID MAKE IT TO A DRAIN THAT IS CONNECTED TO THE SANITARY SEWER ON BUFFALO AVENUE. CONTAMINATED MATERIAL HAS BEEN COMBINED W/CONTAMINATED SOIL FROM SPILL NUMBER 1301719 AND IT WILL BE SAMPLED FOR WASTE CHARACTERIZATION FOR DISPOSAL.|2013-06-11 16:17:00|2013-06-21 18:25:06.813000000|DANIEL RIORDAN|JBI INC.|20 IROQUOIS ST.|NIAGARA FALLS|NY|14303 |001|DANIEL RIORDAN|(716) 289-0003||False