I don't think that you are being realistic about what is involved in the engineering component. The layout floor plan is part of the FEL 1 and is part of the OOM estimate. All of that has to be further defined. Foundations or slabs require an understanding of the geology and soil conditions. That is the Civil. Mechanical and Electrical design follows. #3 was designed by JB out of his machine shop and there are likely no detailed drawings for it. Can't proceed or sell anything that way.

The 2 Million as a percentage of the total correspond exactly to the benchmarks for FEL 2 and FEL 3 phases where this is done. SAIC was just telling it like it is. If you agree with that Summary and take it as gospel (you do don't you?), then you can't selectively disagree with it.

6 mo. to 1 year including commissioning. Don't oversimplify it. There is a safety aspect s well. Can't take shortcuts.