CC tidbits: -The BFS builds in an extra year- -first product in storage: 2015 -first shipment: 2016 -first revenue: "one year later" -financing in the next "weeks and months" complete by the middle of the year -At the present, "90 % of time (to be spent) on financing related activites" -Permits: application end of this month, early next month for mining license -Off takes: hoping to happen by the middle of this year "May-June of 2013" After 4 years, what's another 5 months?