I suppose this is "fluff" taken STRAIGHT from the Signed PO

"Delivery Schedule
Following delivery schedule is agreed between the parties

For CWS Demo Unit:

31.12.2012 Delivery date of 1 CWS Demo Unit

31.01.2012 Arrival of 1 CWS Demo Unit at site for installation and test operation

31.05.2013 Ending of trial run and technology adjustments, feedstock efficiency, etc TBD

For Steam Ray Combustion Engines:

6 months from date of this PO Supplier partial delivery before agreed delivery date is anticipated

SEEMS TO ME THIS AIN'T FLUFF! IN FACT IVE ALREADY HAD MY ATTORNEY LOOK THESE DOCUMENTS OVER AND HE SEEMS TO FEEL THEY LOOK PRETTY DARN LEGALLY BINDING!!!

Go WTWO!