Mill Drain Pond dewatered and backfilled. CHECK
Ore Pad storage area cleared, graded, liner repaired, containment berms reconstructed. Ready for certification. Check
Construction of MSHA safety berms and excavation of the upland drainage ditch for the mill building. Check
Tailings Pond being dewatered. Check
All per plans approved by DRMS via AM-03 and TR-ll Check
GO CGFI