Operation Blue Roof Team Reports
Oct. 6, 0900
Contractors:
Carothers Construction, Water Valley, Miss.
Ceres Environmental
S & M Associates, Pascagoula, Miss.

Service Centers Open: 22-27, depending on need
Mission Requirements: Estimated 47,000
Individual Requests Received (Previous Day): 1,407
Total Requests Received: 39,108
Roofs Installed (Previous Day): 1,322
Total Installed: 23,195
Total Crews: 300-400
Anticipated Days Remaining: 30 (very weather dependent)