The pipeline installation was completed on 10th August 2012 and the sub-sea tie-in was completed and tested on 15th August. All sub-sea valves have been opened ready for flow and the overall installation project was substantially completed on 18th August. The contractors' installation equipment and barges were demobilized on the same day. Hook-up at the platform end is awaiting a replacement flange assembly which is expected to be installed in the next day or so.