InvestorsHub Logo
Followers 5
Posts 295
Boards Moderated 0
Alias Born 11/01/2011

Re: None

Monday, 07/30/2012 9:50:32 AM

Monday, July 30, 2012 9:50:32 AM

Post# of 287
Plains Creek receives Preliminary Economic Assessment for Direct Shipping Option Project for Farim Phosphate Project, Guinea Bissau, West Africa



VANCOUVER, July 30, 2012 /PRNewswire/ - Plains Creek Phosphate Corporation ("Plains Creek", the "Company") (TSX-V: PCP) is pleased to announce the results of a Preliminary Economic Assessment ("PEA") for the Direct Shipping Option ("DSO") Project, the first step in the development of the GB Minerals AG Farim Phosphate Project located in Guinea Bissau, West Africa. The PEA was prepared by GBM Minerals Engineering Consultants Limited ("GBMMEC") in conjunction with Golder Associates Limited ("Golder"), GEEEM Consultants and Tropica Environmental, all of whom are independent of the Company.

Summary of the DSO Project PEA

The Farim Phosphate Project consists of a high grade sedimentary phosphate deposit of one continuous phosphate bed, known as the FPA layer, which extends over a known surface area of approximately 40 km². A Measured and Indicated Resource of 32.60 million tonnes ("Mt") of DSO phosphate has been identified within the Farim Phosphate Project for the DSO Project with a P2O5 grade in excess of 30.7 % and an average R2O3 content of 6.01%.

A 25 year mine life is planned for a total of 12.5 Mt of DSO phosphate (500,000 tonnes per annum), at an average grade of 30.7% P2O5 and less than 6% R2O3. Based on the current Measured and Indicated Resources the potential mine life for the DSO Project can be extended to in excess of 50 years at this production rate, based on the model and assumptions contained in the PEA.

The average strip ratio over the 25 year mine plan is 7.4:1 (bank cubic meters waste: tonne phosphate). The average thickness of phosphate deposit is approximately 4 meters over the life of the DSO Project. Average annual waste production is 3.6 Mm3. The mine plan grade has been optimized to remain above 30% P2O5 for each of the 25 years of mine life.

The current financial model assumes the mining of 12.5 million tonnes which is less than 38% of the recently announced Indicated and Measured DSO Resources. There is also potential to improve the Project economics by increasing the production rate and the life of mine, capital and working costs.

The Farim Phosphate Project has been granted a Mining Lease and a Production License by the Guinea-Bissau Government. This is valuable to optimizing the timetable for development and production.

The DSO Project encompasses the following general process flow:
• Contractor mining;
• Removal of overburden by a combination of excavators and trucks;
• Run of Mine("ROM") phosphate removed by excavators and trucks and stockpiled for loading and blending close to a barge loading system located some 1.5 km from the open pit mine;
• A number of barges moored to a floating pontoon will be loaded and taken to a bulk carrier vessel (of 25,000 tonnes capacity) moored to a floating ship loading facility off the Rio Casheu estuary for dispatch to customers and off takers;
• The river transport distance from the planned barge loading site at the mine site to the Rio Cacheu estuary ship loading facility on the Atlantic Ocean is approximately 150 kilometres; and
• ROM phosphate will also be available for supply to the in-country market as a direct application fertilizer.



PRELIMINARY ECONOMIC ASSESSMENT HIGHLIGHTS
All amounts in US dollars

Table 1: Summary of Physical Parameters of the DSO Project



Physical Parameter

Value



Mine Life

25 Years



Construction Period

1 Year



Operation

300 days per year



Total Life of Mine Production

12.5 million tonnes @ 30.7% P2O5 and = 6 % FeAl phosphate



Annual Sales

500,000 tonnes @ 30% P2O5 phosphate



Revenue Guidance Estimate

US$150 per tonne of phosphate FOB




The mine plan and financial outputs are based on a mining cutoff grade of 29% P2O5 that utilizes approximately 38% of the currently identified Direct Shipping Option Measured and Indicated phosphate mineral resources.

Table 2: Summary of DSO Project Costs



Item

Cost (USD)



Operating Costs





Mining

US$ 31.39 per tonne



Power and Electricity

US$ 8.17 per tonne



General & Admin expenses

US$ 5 per tonne



Marine Logistics

US$ 9.12 per tonne



Total

US$ 53.68 per tonne









Capital costs (life of mine)





Pre-production stripping (incl mobilisation)

US$ 19.27 million



Mine, Marine & Infrastructure (incl contingency)

US$ 58.51 million



Sustaining

US$ 64.75 million



Closure

US$ 5 million



Total Life of Mine capital costs

US$ 147.53 million including contingency



Contingencies

25 %



Royalties 2 %

2 %




Capital costs have been further estimated as follows:

Table 3: DSO Project CAPEX Estimate (Area Breakdown)



Area #

Area Name

Total Capital

[M USD]

Contingency

[M USD]

Total Capital

[M USD]

Percent Total



000

Project General

11.60

1.47

13.07

16.8%



100

Mine

21.91

8.03

34.43

44.3 %



200

Marine Logistics

13.93

8.23

24.97

32.1 %



300

Marine Infrastructure

3.70

1.70

5.40

6.8 %





Total

58.44

19.43

77.87

100 %




Capital estimates include mine facilities and infrastructure, mining equipment, dewatering wells, stockpile loader, dyke construction, stockpile area, and ex-pit haul road construction.

Table 4: Cash Flow Analysis



Units

2013

2014

2015

2016

2017

2018

2019

2020-2039



Production



















Phosphate '000 dry tonne - Sales

100

400

501

500

500

500

500

9,500



Price Phosphate US$/tonne

150

150

150

150

150

150

150

150



Sales US$ '000

15,000

60,450

75,150

75,000

75,000

75,000

75,000

1,425,000



Cost of Sales



















Operating cost US$/tonne

22

58.07

59.39

59.75

57.13

56.93

55.92

52



Total operating cost US$ '000

2,200

23,286

29,754

29,875

28,565

28,465

27,960

494,000



EBITDA US$ '000

12,800

37,164

45,396

45,125

46,435

46,435

47,040

931,000



CAPEX US$ '000

77,780

2,590

2,590

2,590

2,590

2,590

2,590

49,210



Net cash flow before tax and royalties US$ '000

(64,980)

34,574

42,806

42,535

43,845

43,945

44,450

881,790




Considering the DSO Project on a stand-alone basis, the undiscounted pre-tax cash flow totals US$ 1,082 million over the 25 year mine life. Operating cash flow averages US$ 45.36 million per year and simple payback of preproduction capital is achieved after approximately 2 years of operation.

EBITDA as disclosed in the table above is a non-GAAP financial measure and does not have a standardized meaning and is therefore unlikely to be comparable to similar measures presented by other issuers.

The Internal Rate of Return (IRR) is 63%. Pre-tax Net Present Value (NPV) at various discount rates is shown in Table 5.

Table 5: Pre-tax NPV Sensitivity to Discount Rate



Rate

NPV



0 % (Undiscounted)

$ 1,117million



5 %

$ 552 million



10 %

$ 338 million



15 %

$ 179 million



20 %

$ 106. million



25 %

$ 67 million




The economic analysis contained in PEA is based, in part, on Measured and Indicated Resources, and is preliminary in nature. There is no certainty that the resources development, production and economic forecasts on which this PEA is based will be realized.

Mineral Resource Estimates

Summary

The Mineral Resource Estimate for the Farim Phosphate Project was completed by the Qualified Person, Dr. Marcelo Godoy of Golder in Santiago, Chile. Dr. Godoy meets the requirements of a Qualified Person for the purposes of NI 43-101 reporting and is independent from the Company.

The Mineral Resource estimate defines a Measured Resource of 64.6 Mt at an average grade of 29.11% P2O5, an Indicated Resource of 28.1 Mt at an average grade of 27.68% P2O5 and an Inferred Resource of 18.3 Mt at an average grade of 28.66% P2O5. No recoveries or dilution factors have been considered in this estimate and the estimate is strictly in situ, in accordance with NI 43-101 reporting guidelines for resources.

Resource Estimates

The mineral resources reported in this PEA were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and are presented in the Table below.

Table 6: Mineral Resource Statement, Farim Phosphate Deposit, 16 May, 2012



Resource
Class

Block

Tonnage
(Mt)

P2O5
(%)

FPA
(m)

Al2O3
(%)

CaO
(%)

Fe2O3
(%)

SiO2
(%)

Over
burden
(m)

S/R



Measured

North
Of
River

64.6

29.11

3.65

2.78

39.44

5.60

11.39

43.40

12.43



Indicated

North
of River

17.7

26.93

3.15

2.62

40.14

5.19

10.64

39.50

13.18



South
Of
River

10.3

28.96

2.61

5.36

36.37

4.59

11.68

29.05

12.11



Sub
total

28.1

27.68

2.95

3.63

38.75

4.97

11.02

35.65

12.79



Measured
+ Indicated

North
of River

82.3

28.64

3.54

2.75

39.59

5.51

11.23

42.56

12.59



South
Of
River

10.3

28.96

2.61

5.36

36.37

4.59

11.68

29.05

12.11



Sub
total

92.6

28.68

3.44

3.04

39.23

5.41

11.28

41.05

12.54



Inferred

North
of River

3.4

27.36

2.75

2.75

39.30

5.21

11.05

42.70

15.81



South
Of
River

14.9

28.96

2.35

6.30

35.78

4.57

11.64

29.45

13.19



Sub
total

18.3

28.66

2.42

5.64

36.43

4.69

11.53

31.90

13.67




Phosphate mineralization is still currently open to the west and poorly drilled to the south of the River Cacheu.

Key Assumptions and Methods

Golder prepared the Resource Estimate by modeling the Farim resource based on a two dimensional (2D) block model with 125 m x 125 m cells and 25 internal discrete nodes covering the extents of the FPA layer. The extents of the FPA layer were estimated based on the presence or absence of the FPA layer in the drill holes.

Exploratory data analysis and variography were carried out and variables were estimated using a three pass strategy, whereby each successive pass had an increased search radius and less restrictive sample selection criteria. This approach ensures all blocks received a value for each variable. Values were assigned using a combination of Ordinary Kriging and Inverse Distance Weighted methods for the following variables: P2O5; Al2O3; CaO; Fe2O3; SiO2; FPA Thickness; and Overburden Thickness.

The stripping ratio was derived from the estimated overburden and FPA thicknesses. Classification was assigned to each block in the model based on a drilling spacing as follows:
• Measured Resource: Areas with drilling coverage of up to 500 m by 500 m and a P2O5 slope of regression greater or equal 0.65;


• Indicated Resource: Areas with drilling coverage of up to 1000 m by 1000 m and a P2O5 slope of regression greater or equal 0.4; and


• Inferred Resource: Areas within the extents of the FPA and not classified as Measured or Indicated.

A corridor following the Rio Cacheu was excluded and set to "unclassified" due to the uncertainty related to the extraction of material in this area. In addition, the resource estimate was divided into blocks corresponding to the location relative to the Rio Cacheu; "north" or "south".

After applying the above criteria and the for the purpose of public reporting the resources where restricted to a minimum FPA thickness of 1.5 m and a stripping ratio no greater than 20:1. By applying these mining restrictions it is considered that the disclosed mineral resource estimates fulfill the requirement of "reasonable prospects for economic extraction". Due to the consistent grade continuity, with grades above 27% P2O5 , a phosphate cut-off grade was not applied to report the Mineral Resource estimates.

Data Verification

Data verification was carried out by Golder and included independent sampling, a core logging check, drill hole collar survey checks and database integrity checks. No material issues were noted. Golder reviewed the quality assurance and quality control (QAQC) procedures reported from previous exploration campaigns. QAQC procedures and data from GB Minerals AG (which is the subsidiary of the Company that holds the title to Farim Phosphate Project) were reviewed by Golder. GB Minerals AG submitted a total of eight field duplicates and six standards samples in a total of 156 samples. No blanks were submitted.

There is no process design involved in the direct shipping of phosphate by sea transportation. During a site visit in May 2011, Golder reviewed the drilling, logging and sampling procedures employed by GB Minerals AG. A laboratory audit of both the sample preparation and assaying facilities was also carried out by Golder.

Data verification for resources was also extensively covered in the previously filed Technical Report of the Company dated February 10, 2011 filed on SEDAR under the Company's profile at www.sedar.com.

Mining

The majority of the annual rainfall over the DSO Project area is concentrated in the period from July through September, and the DSO Project mine plan will carry out mining activities for 10 months out of the year to avoid the inefficiencies of mining during the higher rainfall months. Installed mining equipment capacity has been designed to produce the annual plan phosphate requirements and associated waste stripping within the 10 drier months of the year.

Key design elements of the DSO mining plan are water management and haul road maintenance. All mining areas must be fully dewatered in advance of mining activities. The proximity of the mine to the Rio Cacheu will require the construction of a protection dyke to prevent in-pit flooding.

Contractor mining has been selected, for the excavator / truck mining method for the DSO mining plan based on flexibility, lower initial capital, lower investment risk, grade control, and the ability to blend quality for required product specifications. Contractor mining has been proposed to minimize capital investment and to shorten the period to production which could arise from the availability of mining capital equipment and the shortage of in country manpower skills.

The remote nature of the Project, with limited power supply, precludes the use of electric mining equipment and all mining equipment selected for the DSO Project is diesel mobile equipment.

This mining method uses excavators and trucks to handle 100% of the overburden and DSO phosphate. Waste will be stripped and removed with 11 m3 to 12 m3 bucket front-end loaders or small hydraulic excavators matched with 50 ton haul trucks. The DSO phosphate will be mined with 3 m3 to 4 m3 bucket class backhoes matched with 35 t trucks.

ROM phosphate will be removed by excavators and trucks to a 20,000 tonne ROM pad for storage and blending. The ROM pad is located some 1.5km from the open pit and adjacent to the barge loading facility.

The DSO operation will mine 0.5 Mtpa of phosphate and will require a waste storage facility capable of holding 34 Mm3. The facility will be approximately 25 m high with a footprint of 1000 meters by 1500 meters.

Beneficiation

The ROM phosphate will be mined, blended if necessary and will be directly shipped with limited treatment or processing (if any).

Project Infrastructure and Product

The infrastructure requirements associated with the DSO project include the mine infrastructure, mine camp, offices, workshops, water treatment facilities, power generation and water supply.

River Transport and Loading

Transfer of phosphate from the ROM pad to the feed hopper of the barge loading facility will be by front end loader. The hopper will feed a conveyor system to load 2,700 t non-propelled barges. Sets of barges will then transport with the aid of a pusher tug down the Rio Cacheu to a seagoing vessel.

The barges will be unloaded by the seagoing vessel anchored to a floating ship loading facility beyond the shallow waters (+ 12 meter deep) using clam shell unloaders. Possible mooring points accessible to vessels of capacity up to 25,000t have been identified in the estuary of the Rio Cacheu.

Recommendations

The results of the Preliminary Economic Assessment show that the DSO Project is robust from a technical and economic standpoint at the selected long term phosphate prices, and GBMMEC has recommended that the DSO Project continues to be advanced to the Feasibility Stage and that a production rate of 1 Mt per annum be investigated.

Qualified Persons

Dr. Marcelo Godoy, MAusIMM (CP) of Golder in Santiago, Chile, who is a Qualified Person as defined in NI 43-101, prepared and is responsible for the Mineral Resource Estimate for the Farim Phosphate Project as disclosed in this news release. In addition, the following other Qualified Persons prepared (or supervised and approved the preparation thereof) and are responsible for other parts of the PEA, which are referred to in this news release: Michael Short, FIMMM, C.Eng. of GBMMEC, Ian Jackson, B.Eng, ACSM, C.Eng., MIMMM (CP) of GBMMEC, Richard Elmer, C.Eng., MIMMM (CP) of Golder, and Terry Kremmel, PE (MO and NC), SME (CP) of Golder. All of these Qualified Persons are independent from the Company.

About Plains Creek Phosphate Corporation

Plains Creek Phosphate Corporation is a Canadian mining and exploration company focused on advancing the Farim Phosphate Project located in Guinea-Bissau, West Africa. The Farim Project currently comprises a phosphate deposit consisting of one continuous flat lying phosphate bed with a NI 43-101 compliant Mineral Resource estimate that defines a Measured Resource of 64.6 MT at an average grade of 29.11% P2O5, an Indicated Resource of 28.1 Mt at an average grade of 27.68 % P2O5 and an Inferred Resource of 18.3 Mt at an average grade of 28.66 % P2O5. A two phased development is planned for the Farim Phosphate Project as an open pit mining operation. Phase One consists of a Direct Shipping Option Project with an annual phosphate production of 0.5 Mt per annum and Phase Two which consists of the production of 2 Mt per annum of phosphate rock concentrate and includes a beneficiation plant and associated infrastructure, pipeline and port.

The Company's shares are listed on the TSX Venture Exchange under the trading symbol "PCP". For additional information, please visit us at www.plainscreek.com.

ON BEHALF OF THE BOARD

(Signed) "Carson Phillips"
Carson Phillips
Vice-President, Corporate Development and Director

Cautionary Statement

Statements in this release may be viewed as forward-looking statements. Such statements involve risks and uncertainties that could cause actual results to differ materially from those projected. There are no assurances the Company can fulfill such forward-statements and the Company undertakes no obligation to update statements. Such forward looking statements are only predictions; actual events or results may differ materially as a result of risks facing the Company, some of which are beyond the Company's control. In addition, pursuant to National Instrument 43-101, the Company cautions that mineral resources that are not mineral reserves do not have demonstrated economic viability.

The reader should be cautioned that there are risks that could affect the potential development of the Project's mineral resources, which include: the political instability in Africa and Guinea Bissau in particular, which is where the Project is located; and that additional financing will be required to ultimately develop the Project and the ability to obtain such financing on favorable terms will be affected by prevailing market conditions. A more detailed discussion of such risks are outlined in the Company's Filing Statement dated February 22, 2011 which is filed under the Company's profile on SEDAR at www.sedar.com.

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

SOURCE Plains Creek Phosphate Corp.

Join the InvestorsHub Community

Register for free to join our community of investors and share your ideas. You will also get access to streaming quotes, interactive charts, trades, portfolio, live options flow and more tools.