According to the company's website, it can be produced in as little as 3 weeks. But as you pointed out, the plan is to purchase an existing used structure. Production time drops to zero. Cost (your quote) approx. $225,000.
Transportation costs will be minimal since this is a "knock down" modular design. At most 2 semi trucks. Cross country trip would be way less than $15,000, but let's call it $20,000.
Assembly time 3 to 5 days!! Now even if you have 10 workers and double the company estimate, and they take 10 days to assemble, that would put labor costs at over $750,000 to reach your stated cost of a million dollars!!!
With an 8 hour day, 100 man days (10 men X 10 days X 8 hours) would would be 800 man hours. The average pay would need to be about $940 per hour to come close to your ridiculous claim! (Give me that job! I want $940 per hour!!)
Where ever you came up with this figure from, you should recheck your calculations and sources. Your claims could not be more wrong. Your post is giving erroneous information or is this figure just an opinion?