Orsu Announces Positive Definitive Feasibility Study for the Karchiga VMS Copper Project in Kazakhstan
Orsu Metals Corporation (TSX:OSU)(AIM:OSU) -
Highlights:
-- Post-tax NPV7.5 of US$150 million, IRR of 30% (based on price of
US$3.25/lb Cu);
-- Initial capital expenditure of US$115 million;
-- Payback period of 2.75 years (on initial capital expenditure);
-- 11.5 years mine production of 149kt (328 Mlb) payable copper:
-- average annual production of 13kt (28.6 Mlb) of copper from sulphide
and oxide ore;
-- at a processing rate of 750,000 tonnes of sulphide ore per annum, a
total of 136.3kt (300 Mlb) of copper in 27.9% concentrate;
-- at a heap leach processing rate of 360,000 tonnes of oxide ore per
annum (over 4.5 years), a total of 12.7kt (27.9 Mlb) of cathode
copper;
-- Life of mine cash operating cost (pre tax) of US$1.47/lb Cu;
-- Net smelter revenue over the life of mine of US$971 million.
FEATURED POET Announces Design Win and Collaboration with Foxconn Interconnect Technology for High-speed AI Systems • May 14, 2024 10:09 AM
FEATURED Element79 Gold Corp Reports Exceptionally High-Grade Results from Lucero • May 14, 2024 7:00 AM
VAYK Added New Manager for Expansion into $64 Billion Domestic Short-term Rental Market • VAYK • May 14, 2024 9:00 AM
Avant Technologies Equipping AI-Managed Data Center with High Performance Computing Systems • AVAI • May 10, 2024 8:00 AM
VAYK Discloses Strategic Conversation on Potential Acquisition of $4 Million Home Service Business • VAYK • May 9, 2024 9:00 AM
Bantec's Howco Awarded $4.19 Million Dollar U.S. Department of Defense Contract • BANT • May 8, 2024 10:00 AM