Fairly soon in deep water is not very fast. Total took 4.5 to 5.5 years to develop the drilling plan for Akpo, after spending five years in exploration phase. It took two years to order and have built the FPSO. The 44 wells were drilled by two drill ships over a three plus year period.
The JDZ is a lot of teritory to explore and develop, even if you have the drill ships available.