UPDATED FACTORY PICS 7/15/11
Was able to swing by the factory today and based by what I saw (see pics below)there has been a lot of work accomplished. I was also able to speak with the owner of the general contracting company doing the construction work. He stated they are on track to be finished on time for the July 28th grand opening.

[url=http://xs.to/photo/55814][/url]
Burning machine being assembled. This is the machine that the LED lights will be tested in.

[url=http://xs.to/photo/55819][/url]
Assembly area. Floor is now complete and the assembly tables are ready to be assembled.

[url=http://xs.to/photo/55820][/url]
Break room for factory workers is being completed.

[url=http://xs.to/photo/55821][/url]
Area where grand opening will take place. Ceiling, walls and floor being painted. This is the Phase II expansion area for factory.

[url=http://xs.to/photo/55822][/url]
Looking into the executive offices. Lights being installed.