Casposo - OPERATIONS UPDATE (As at 31 December 2010)

* Poured first gold in November.
* Ramp up to full production slower than forecast.
* Expect to reach full production rates in April, 2011.
* Mined ore stockpiles of 97,648t at 8.21g/t Au and 86.89g/t Ag or 9.45g/t Au_eq.
* Doré production of 140kg (~9% Au and 88% Ag).