TOB, the whole development seem to have been engineered, the FPSO was ordered in mid 2005 and delivered in January of 2007. The Deepwater Discovery started drilling wells in 2006, total planned on 2000 rig days of drilling and added the Jack Ryan drillship in 2007 for 44 wells. YThe materials casings, manifolds risers etc was staged to arrive as the wells were drilled.