The potential for positive cash flow is good. They will need it first and foremost to address their NJEDA Bond Defaults.....and they need to to that soon.

From last 10Q:

In addition, the Company has received Notice of Default from the Trustee of the NJED Bonds as a result of the utilization of the debt service reserve being used to pay interest payments due on September 1, 2009, March 1, 2010 and September 1, 2010 totaling $121k, $113k and $113k, respectively, and principal payments due on September 1, 2009 totaling $210k. The debt service reserve was utilized to make such payments as a result of the Company’s not having sufficient funds available to make such payments when due.

The Company did not have sufficient funds available to make the principal payments due on September 1, 2010, totaling $200k and requested that the Trustee withdraw such funds from the debt service reserve. The Company’s request was denied and accordingly the principal payment due on September 1, 2010, totaling $200k was not made.

The Company has requested a postponement of principal payments due on September 1, 2010, 2011 and 2012, with an aggregate of all such postponed principal payments being added to the principal payments due on September 1, 2013. Resolution of the Company’s default on the NJEDA Bonds and our request for postponement of principal payments will have a significant effect on our ability to operate in the future.

Please refer to Note 5 to our financial statements for a more detailed discussion of the NJEDA Bonds and Notice of Default. Please also note that the working capital deficit of $2.6 million as of September 30, 2010, includes the entire principal amount due in relation to the NJEDA Bonds. This amount, totaling $3.4 million was first classified as a current liability as of March 31, 2010, due to the Notice of Default received from the Trustee in relation to the NJEDA Bonds.

NOTE 5
- NJEDA BONDS

On August 31, 2005, the Company successfully completed a refinancing of a prior 1999 bond issue through the issuance of new tax-exempt bonds (the “Bonds”). The refinancing involved borrowing $4,155,000, evidenced by a 6.5% Series A Note in the principal amount of $3,660,000 maturing on September 1, 2030 and a 9% Series B Note in the principal amount of $495,000 maturing on September 1, 2012. The net proceeds, after payment of issuance costs, were used (i) to redeem the outstanding tax-exempt Bonds originally issued by the Authority on September 2, 1999, (ii) refinance other equipment financing and (iii) for the purchase of certain equipment to be used in the manufacture of pharmaceutical products.

Interest is payable semiannually on March 1 and September 1 of each year. The Bonds are collateralized by a first lien on the Company’s facility and equipment acquired with the proceeds of the original and refinanced Bonds. The related Indenture requires the maintenance of a $415,500 Debt Service Reserve Fund consisting of $366,000 from the Series A Notes proceeds and $49,500 from the Series B Notes proceeds. The Debt Service Reserve is maintained in restricted cash accounts that are classified in Other Assets. $1,274,311 of the proceeds had been deposited in a short-term restricted cash account to fund the purchase of manufacturing equipment and development of the Company’s facility. As of September 30, 2010, all of these proceeds were utilized to upgrade the Company’s manufacturing facilities and for the purchase of manufacturing and laboratory equipment.

Bond issue costs of $354,000 were paid from the bond proceeds and are being amortized over the life of the bonds. Amortization of bond issuance costs amounted to $3,533 and $7,065 for the three and six months ended September 30, 2010, respectively. Amortization of bond issuance costs amounted to $3,533 and $7,065 for the three and six months ended September 30, 2009, respectively.

The NJED Bonds require the Company to make an annual principal payment on September 1 st of varying amounts as specified in the loan documents and semi-annual interest payments on March 1 st and September 1 st , equal to interest due on the outstanding principal at the applicable rate for the semi-annual period just ended.

The interest payments due on September 1, 2009, March 31, 2010 and September 1, 2010, totaling $120,775, $113,075 and $113,075, respectively were paid from the debt service reserve held in the restricted cash account, due to the Company not having sufficient funds to make such payments when due.

The principal payment due on September 1, 2009, totaling $210,000 was paid from the debt service reserve held in the restricted cash account, due to the Company not having sufficient funds to make the payment when due. The Company did not have sufficient funds available to make the principal payments due on September 1, 2010 totaling $200,000, and requested the Trustee to withdraw the funds from debt service reserve held in the restricted cash account and to utilize such funds to make the principal payment due. The Company’s request was denied by the Trustee. Accordingly, the principal payment due on September 1, 2010, totaling $200,000 was not made.

Pursuant to the terms of the NJED Bonds, the Company is required to replenish any amounts withdrawn from the debt service reserve and used to make principal or interest payments in six monthly installments, each being equal to one-sixth of the amount withdrawn and with the first installment due on the 15 th of the month in which the withdrawal from debt service reserve occurred and the remaining five monthly payments being due on the 15 th of the five immediately subsequent months. The Company has, to date, made all payments required in relation to the withdrawals made from the debt service reserve on September 1, 2009, March 1, 2010 and September 1, 2010. The Company is required to make four additional monthly payments of $19,330 during the period November 15, 2010 through February 15, 2011, in order to fully replenish the September 1, 2010 withdrawal from the debt service reserve.


F - 8


The Company does not expect to have sufficient available funds to make the interest payment of $113,075 due on March 1, 2011 as well as the principal payment of $200,000 which was due, but not paid, on September 1, 2010

The Company has received Notice of Default from the Trustee of the NJED Bonds in relation to the withdrawals from the debt service reserve, and has requested a postponement of principal payments due on September 1 st of 2010, 2011 and 2012, with an aggregate of all such postponed principal payments being added to the principal payments due on September 1, 2013. Resolution of the Company’s default under the NJED Bonds and our request for postponement of principal payments will have a significant effect on our ability to operate in the future.

Due to issuance of a Notice of Default being received from the Trustee of the NJED Bonds, and until the event of default is waived or rescinded, the Company has classified the entire principal due, an amount aggregating $3.385 million, as a current liability.