Permalink Reply by Ray Broadbent 1 day ago
600,000 shares traded friday...5 times normal volume. This is extremely interesting.
Permalink Reply by Skip Peel- Independent Landman 14 hours ago
Why?? Mainland Resources, Burkley-Phillips #1 reported 91 days drilling ahead @ 17,875' on 10-22-10.
Permalink Reply by FXEF 14 hours ago
Skip,
Thanks for your reports. Only 72' last week, do you get any other status information that might explain the slow down.
Permalink Reply by Skip Peel- Independent Landman 11 hours ago
You're welcome. No, the preprietary report that I subscribe to only reports what I post. Details must come from company announcements. There are numerous possible reasons for only 72' in additional depth. Maybe one of our drillers can tells us how long a 17,800' pipe trip takes.
Permalink Reply by rusell shleby 9 hours ago
They spent the week setting pipe to enter the next formation. No drilling was done.
Permalink Reply by ShaleGeo 1 hour ago
This is the start of the section that Chevron had trouble with. You can refer to the log I posted earlier to see how long it took them to drill this section.
Jay