SHOULD REACH 19,200 FT EARLY NEXT WEEK
On 10/14 SHALEONYOU reported 1,100 ft to go to reach casing point at 19,200. At rate of approximately 100 ft per day, that point should be reached 10/25 or 26th. Allowing two weeks to set and cement casing and do wirline work, MNLU should be off and running the next 3,000 ft to TD of 22,000 ft. I hope that depth can be reached by mid December. So am hoping for that big XMAS present but not holding my breath. Maybe a reason to break out champagne for New Year's celebration.