MileHigh. Updated Website Jan 25.
I assume the company will release full Product Descriptions in conjunction with their new Website on Jan 25.

Delivery Schedule

As of today, the defined timeline has been agreed upon by both our contracted vendors and in-house personnel:

1) One innoculant "Wall Photobioreactor" is scheduled to be completed by the third week in January; this Photobioreactor will generate sufficient mass to seed the 6000 sq ft in Santa Ana

2) 1200 (sufficient for 4 acres) -- 180 degree "corners" will be shipped to BEHL by the end of this month (the funds for this purchase have already been placed in escrow for delivery)

3) The specialty designed gasket and clamp have been designed and will be shipped to BEHL by the end of this month (the funds for this purchase have already been placed in escrow for delivery)

4) The first mile + of custom tubing will arrive by the third week of this month (the funds for this purchase have already been placed in escrow for delivery)

5) The sensors for the Photobioreactor in Santa Ana are in-house

6) The newly designed harvesting solution will be delivered to Santa Ana by the end of the month (the funds for this purchase have already been placed in escrow for delivery)

7) The anticipated completion build date for the 6000 sq ft in Santa Ana is for the second week in February

8) The company website is being presently updated; anticipated completion date is January 25th.