Just a caution on production capacity. What the company said is that given their experience with building the first turbines, is is feasible to build 30 turbines per month.

I don't think, however, that they presently have that production capacity in place and rather expect them to build the necessary facility over the coming months, now that they do have the $19 million from the recent financings.

So in my view, it will take much longer than 6 months to fill the initial orders of 128 turbines, but production will speed up as they add to capacity. We will reach a clip of 30 turbines per month soon enough.