The cased vertical portion and the radius bend should take no more than 2 days including running the casing and cementing in place. The first rig is done at this point and moves on. Then 5 days to cure the cement would be reasonable.

The horizontal drill rig then moves in to drill the 2000' lateral. I doubt this would take more than 2-3 days. I am not clear if they then run a slotted liner or how they complete / case the lateral portion of the well and the timeframe for that.