Bureiskaya GES ups FOREM deliveries to 701 mln kWh over the H1, 7% above the target. 06 July 2004 13:00 Bureiskaya GES widened its actual deliveries of electric power on FOREM to 701 mln kWh by H1 results, 7% above the target, Bureiskaya GES said. The indicators have risen due to the additional loading target set by RAO UES. Bureiskaya GES' construction started in 1985, 2 hydroelectric generators were launched in summer of 2003. 1.25 bln kWh have been produced to-date. The 3rd generator will be put in operation in Nov. of 2004 while the final completion of the project is scheduled for 2009.