Zhanjiang update -- Next week, company officials will be going to Zhanjiang to approve the layout of Phase I of the wind farm in order to start construction of the trunk roads, foundations and collector system. The project will require the installation of more met towers to accommodate the expansion of the project beyond 49 MW. Welwind officials will be meeting with Government officials to finalize the PPA next week