InvestorsHub Logo
Followers 4
Posts 1436
Boards Moderated 0
Alias Born 09/28/2006

Re: None

Thursday, 07/10/2008 1:04:58 PM

Thursday, July 10, 2008 1:04:58 PM

Post# of 8034
WWEI

Get in now before next week

Zhanjiang update -- Next week, company officials will be going to Zhanjiang to approve the layout of Phase I of the wind farm in order to start construction of the trunk roads, foundations and collector system. The project will require the installation of more met towers to accommodate the expansion of the project beyond 49 MW. Welwind officials will be meeting with Government officials to finalize the PPA next week.
Join InvestorsHub

Join the InvestorsHub Community

Register for free to join our community of investors and share your ideas. You will also get access to streaming quotes, interactive charts, trades, portfolio, live options flow and more tools.