I can't build it or finish it until I have all the equipment. It doesn't make sense to start and stop. The required labor for assembly is cheap, maybe 30k, which is small in the overall scope. It also needs to be tweaked to meet it's application, feedstock type, location, heat source, electric source, etc. It's not as simple as you may think. It's twice the machine than is contracted (per their requested changes) and the scope changes would need to be agreed and added before it would ship. The start up, freight, install, crane, electrical, training, tank farm, loading, unloading, electric for that, etc is all on top of the 375k.