Additional data, corrections, and pics ---------------------

My note taking is scrambled so I hope I get it all this time.

Add to equipment on site:
D-6 Cat with dozer blade
Fork lift - probably 2 ton capacity

Corrections:
Mill site is 27 acres, not 5 acres
'Drill analysis' should have read 'sample analysis' - the drilled holes were small and shallow
There are 2 each 6 X 6 ball mills and one each 4.5 X 6

Mine site:
The mining is hard rock, drill and blast. Mining will be pillar and room style
Deposit is flat lying "manto" type deposit with 25 meter exposed width

The primary crusher circuit and screener could handle about 1,200/ton/day. So, by upsizing ball mills, gravity tables, and additional flotation cells, the throughput could be in that 1200 ton range/day

I'm not very computer literate, but I managed to get the pics up with a public URL and most of them have captions underneath:

http://www.myspace.com/cl99cl

Below the picture, click on the hypertext "view my pics"