Baja Mining completes feasibility study


2007-05-29 09:38 MT - News Release

Mr. John Greenslade reports:

BAJA MINING COMPLETES DEFINITIVE FEASIBILITY STUDY; ROBUST ECONOMICS CONFIRMED

Baja Mining Corp. (the "Company") is pleased to announce the completion of the Definitive Feasibility Study ("DFS") for the Boleo project located at Santa Rosalia, Baja California Sur, Mexico. The DFS is based on long-term prices of $1.50/lb copper, $15/lb cobalt and $1,200/t zinc sulphate, unless otherwise stated. All dollar amounts are in United States dollars.

Highlights:

 
Commercial life of mine average cash cost of negative $0.07/lb of produced copper, net of by-product credits;
Direct capital costs of $407 million, an increase of only 2.5% above the capital costs outlined in the Company's January 2007 Updated Preliminary Economic Analysis ("PEA");
Average annual production, for the first four years of full production:
Copper cathode: 55,750 tonnes;
Cobalt cathode: 1,535 tonnes; and
Zinc contained metal: 6,300 tonnes
Proven and probable reserves provide for 25-year mine life;
More than 275 million tonnes of measured and indicated resources grading 1.77% copper equivalent;
More than 250 million tonnes of inferred resources grading 1.29% copper equivalent;
After-tax IRR of 24.7%, or 46.0% at current market prices;
After-tax NPV (at 8% discount rate) of $700 million or $2.3 billion at current market prices;
Upside from potential manganese production is still available and will increase the base case NPV by an additional $302 million; and
Manganese (contained in manganese carbonate) production could exceed 100,000 tonnes/year at the current design capacity.

John Greenslade, President, commented: "The company is pleased with the improvements confirmed since the Updated PEA, particularly with the increased resource estimate that will facilitate increased near-term copper production. The DFS has confirmed Boleo's already robust economics while keeping capital costs in check. Baja Mining is now firmly positioned to complete the financing and construction of the Boleo Project and we look forward to bringing the Project into production."

DFS Advisors

The DFS incorporates capital and operating cost estimates prepared by Bateman Engineering ("Bateman") and Wardrop Engineering ("Wardrop") for the process plant and mine plan developed by Agapito Associates, Inc ("AAI"), Australian Mine Design and Development ("AMDAD") and Wardrop in accordance with NI 43-101 standards.

Project Description

The Boleo Cu-Co-Zn-Mn Project is located on the east coast of Baja California Sur, Mexico near the town of Santa Rosalia. The deposit contains seven (7) mineralized seams ("mantos"), stacked within a single formation, all dipping gently to the east towards the Sea of Cortez in a step-like fashion, due to post depositional faulting.

The Project consists of approximately 11,000 hectares of mineral concessions and 7,000 hectares of surface occupancy rights, each assembled as a contiguous titled block. The Project is located within the "buffer zone" of the El Vizcaino Biosphere, a Mexican National environmental reserve. An Environmental Impact Manifest (EIM) was submitted in early 2006, and approved by the Mexican authorities in December 2006. The Company has also received authorization to commence development of the Project within the Biosphere.

The Project is to be developed as a series of underground mines using conventional soft rock mining methods, after which small open-cut mines will feed ore to a processing plant utilizing a two stage leaching circuit followed by solid/liquid separation and Solvent Extraction Electrowinning to produce copper and cobalt as LME Grade metal and zinc as zinc sulphate.

Resource Model

Updated resource estimates (April 2007) have been prepared by Hellman & Schofield Pty Ltd ("H&S") that include all results of the 2006 in-fill drill program. Total Measured and Indicated resources have increased to a level sufficient to support a 25 year project life.

Total reported Measured, Indicated and Inferred resources, estimated using 3D block models, are based on Copper equivalent (CuEq) cut-off grade of 0.5%. (CuEq equals Cu plus 15Co/1.50 plus 1.20Zn/1.50)1. The block models were used for open cut mine design.

 
Description Tonnes CuEq.% Cu% Co% Zn% Mn%
Block Model (x millions)

Resources
Measured 74.6 2.09 0.93 0.08 0.48 2.72
Indicated 202.6 1.65 0.62 0.05 0.66 3.10
Total M & I 277.2 1.77 0.70 0.06 0.62 3.00
Inferred 253.2 1.29 0.39 0.04 0.63 2.65

1. Mn is not considered in the equivalency formula.


For underground mine planning purposes, gridded seam models were produced to target higher grade copper mineralization situated towards the base of each manto in order to enable higher copper production and reduce dependence on by-product credits in the early years of the project. Gridded seam model resources are contained within the above block model and are not in addition to it. Resources for the gridded seam models follow and are based on the same CuEq cut-off and CuEq formula as used for the block models.

 
Description Tonnes CuEq.% Cu% Co% Zn% Mn%
Seam Model (x millions)

Resources
Measured 61.1 2.39 1.17 0.08 0.55 2.58
Indicated 85.8 2.02 0.84 0.06 0.73 3.13
Total M & I 146.9 2.17 0.97 0.07 0.66 2.90
Inferred 85.6 1.67 0.52 0.05 0.81 3.10

1. Mn is not considered in the equivalency formula.


Under NI 43-101 that portion of the Block and Seam resource models covered by mine plans are allowed to be classified as reserves. The following reserves are contained within the above resource models and are not separate from them. The same copper equivalent cut-off grade of 0.5% and copper equivalent formula have been used (CuEq equals Cu plus 15Co/1.50 plus 1.20Zn/1.50)1.

 
Description Tonnes CuEq.% Cu% Co% Zn% Mn%
Block Model (x millions)

Open Cut
Reserves
Proven 11.1 2.03 0.75 0.10 0.37 2.74
Probable 6.5 1.75 0.70 0.07 0.48 3.08
1. Mn is not considered in the equivalency formula.

Description Tonnes CuEq.% Cu% Co% Zn% Mn%
Seam Model (x millions)

Underground
Reserves
Proven 29.8 2.54 1.69 0.08 0.46 2.38
Probable 37.6 2.19 1.34 0.07 0.69 3.36

1. Mn is not considered in the equivalency formula.


Mining

Both surface and underground mining operations are planned for extracting ore for the first 25 years at a full mining rate exceeding 3.1 million dry metric tonnes per annum. Approximately 68 million tonnes of ore will be mined from underground operations and 9 million tonnes from surface open cuts. Approximately 18.8 million tonnes of limestone will also be quarried for use in the plant process.

Geotechnical information on the seam formation and low material strength of the mantos suggested that conventional "soft rock" mining methods such as those used in underground coal, potash or salt mining would be successful. Room-and-pillar mining using continuous miners was chosen because of the method's flexibility for changing layout designs, its efficient recovery of resources and lower initial capital cost. The resource block seam model was used to define manto areas that could be mined.

Underground mining plans for high grade copper targets have been prepared for mantos 1, 2, 3 and 4 by AAI. These plans focus on a strategy based on advancing a narrow set of mine workings into areas identified with high grade copper and then retreat mining the mantos and allowing the ground to collapse after removing the ore.

Surface mining plans for mantos 2, 3a, 3aa, and 3, as well as the limestone quarry have been prepared by AMDAD. The first 25 years focus on first providing limestone rock to the plant process and then manto ore after underground mined ore grades fall to comparable levels.

Process plant

The process plant is being designed to treat 3.1 million dry metric tonnes per annum at a head grade of 2.2% copper, 0.1% cobalt and 0.6% zinc through an integrated hydrometallurgical facility to produce LME Grade `A' copper cathode; high purity (greater than 99.8% Co) cobalt cathodes and zinc sulphate monohydrate. A conservative ramp-up rate of 4 years is assumed before achieving design throughput of ore, however the run-of- mine ore grades are highest in these years and copper production will still reach the capacity of the electrowinning circuit by year three (3). Recovery of cobalt and zinc will commence in year 2, allowing an accelerated construction schedule for copper production and a focused technical effort on the start-up of the copper circuit.

The process plant design includes a 2,400 tonnes/day (t/d) acid plant with a cogeneration facility to produce electrical energy from the burning of sulphur. It is expected that the acid plant will generate essentially all of the power requirements of the process and electrowinning plants as well as the desalinated water requirements. The leach circuit will utilize sea water. The potential value of carbon credits that may be available from the use of a heat recovery system to increase the production of power has not been incorporated into the economic analysis of the project.

Marketing of the copper and cobalt products is assumed to be through a metal trading company as an off-take partner. "Expressions of Interest" have been received from several potential partners and it is expected that transfer of title for the products would occur at, or close to, the plant gate to assist the company with minimizing working capital requirements. Marketing of zinc sulphate is assumed to be done by agents who are expert in the business and allowances have been made for freight to the markets and agents' commissions in the net price received.

Capital Costs

Capital costs have been prepared by Bateman, Wardrop, AMDAD, AAI and the Company. The estimated direct capital cost of the project, excluding working capital requirements, is $407 Million. The total project cost, including Engineering, Procurement, and Construction Management, Owner's Costs, and 12.5% overall Contingency is $568 Million. A summary of capital costs is listed in the table.

 
Project Area Capital Cost

Overall Site $39,142,000
Mining $59,678,000
Process Plant $160,322,000
Site Services $94,285,000
Buildings $14,956,000
Construction
Indirects and Freight $39,063,000
------------
Direct Field Costs $407,446,000

EPCM $45,805,000
Contingency $62,349,000
Owner's Costs $36,773,000
Mine Pre-development $16,019,000
------------
Total DFS Value $568,392,000

Mine and Mine Pre-Development capital costs are as at April 30, 2007.
The remainder of capital costs are as at July 31, 2006, and exclude escalation.


Production and Operating Costs

Start-up of the process plant is scheduled for end of second quarter, 2009. Provision has been made for a ramp-up to full production capacity over the first four years. No cobalt or zinc sulphate production is scheduled in year one, with recoveries reduced in year two, while the cobalt and zinc circuits are being brought into production. As the first year is a partial year of production, it has not been included in the following tables.

 
BASE CASE PRODUCTION SUMMARY

Yrs 2-5 Yrs 6-10 Yrs 11-15 Yrs 16-20 Yrs 21-25 Average

Ore treated (kt/y) 2,828 3,120 3,120 3,120 3,120 3,071

Grade: % Cu 2.15 1.80 1.60 1.05 0.93 1.52
% Co 0.071 0.067 0.074 0.091 0.084 0.076
% Zn 0.36 0.46 0.59 0.61 0.77 0.57
% Mn 2.02 2.50 2.46 3.30 4.21 2.93

Production (t/y):
Copper 55,755 51,389 45,486 29,909 26,391 41,204
Cobalt 1,535 1,644 1,796 2,222 2,061 1,865
Zinc Sulphate 17,917 26,702 34,361 35,692 45,131 32,546

UNIT OPERATING COSTS, WITHOUT MN PRODUCTION
(expressed in $/tonne of ore treated)
 
Yrs 2-5 Yrs 6-10 Yrs 11-15 Yrs 16-20 Yrs 21-25 Average

Mining $9.87 $7.67 $8.15 $7.94 $5.10 $7.62
Process $20.80 $20.51 $20.87 $19.77 $22.83 $20.96
G&A, Sales $1.56 $1.71 $1.98 $2.02 $2.34 $1.94
Total ($/t) $32.24 $29.89 $30.99 $29.72 $30.72 $30.53
Cash cost* $/lb $0.18 $0.06 $(0.04) $(0.36) $(0.48) $(0.07)
Cash Flow
$000/yr $196,925 $116,007 $107,086 $85,661 $89,303 $115,749

*Cash cost/lb of Cu is net of cobalt and zinc credits. Cash flows are after-tax,
using Base Case prices of $1.50/lb Cu, $15/lb Co and $1,200/tonne ZnSO4.

When production of manganese carbonate commences the costs shown above will increase somewhat due to the requirement for additional reagents (soda ash) and distribution costs of the product. The estimated production, and costs, when manganese is recovered are shown in the table above.


PRODUCTION AND COSTS, WITH MN PRODUCTION
(assuming Mn starts in 2011)
 
Yrs 2-5 Yrs 6-10 Yrs 11-15 Yrs 16-20 Yrs 21-25 Average

MnCO3 production 66,673 134,359 132,446 177,304 226,365 144,603
Mn contained 30,866 63,149 62,250 83,333 106,392 67,693
Unit Op cost ($/t) $37.54 $39.73 $40.69 $42.71 $46.85 $41.73
Cash cost* of Cu $(0.04) $(0.44) $(0.60) $(1.49) $(2.12) $(0.77)
Cash Flow
$000/yr $217,817 $156,544 $147,208 $139,077 $158,953 $161,674

*Cash cost/lb of Cu is net of by-product credits. Cash flows are after-tax, using
Base Case prices of $1.50/lb Cu, $15/lb Co and $1,200/tonne ZnSO4.


Project Economics

Project economics are presented for four cases: 1) Base Case; 2) Base Case with Manganese production; 3) Five Year Average (three year trailing plus two year leading) Price case; and 4) the current prices scenario. No manganese production is assumed for cases three and four.


Base Case: Base Case economics for the project have been developed using long-term metal prices of $1.50 per pound of copper, $15.00 per pound of cobalt, and $1,200 per metric tonne of zinc sulphate monohydrate. The LME five year forward price curve for copper has been used for pricing in the first three years of production with an extrapolated transition to the long term price in the fourth year.
Base Case with Manganese Recovery: The Boleo deposit is endowed with a rich resource of manganese which is now being recognized as being in short supply. Manganese prices have more than doubled in recent months and manganese metal is now selling in the US in excess of $4,000/tonne. The process selected for the project enables recovery of manganese (as manganese carbonate) with very little additional capital investment (approximately $20 Million) and utilizes uncomplicated technology. The market for manganese carbonate is limited but the material can be further processed into metal, electrolytic manganese dioxide (EMD), or manganese sulphate. For the purpose of evaluating this project it has been assumed that manganese carbonate can be sold, as an intermediate product, for $650/tonne and that it will be necessary to ship it offshore for further processing. The assumed price is less than one third of the current value of the contained metal to allow for third party conversion costs and a potential decline in overall prices from current levels.
Five Year Price Case: For comparison purposes the project economics are also shown using the weighted average three year trailing plus two year leading price for copper and cobalt ($2.25/lb and $16.00/lb). No manganese production is assumed for this case.
Current Price Case: The Base Case prices are considerably lower than current prices, which as of mid-May, 2007 are approximately $3.50/lb for copper, $30.00/lb for cobalt, and $1,500/tonne for zinc sulphate. A case is shown using current prices but the Company does not expect that current prices will be sustained over the long term and the case is shown for comparative purposes only. No manganese production is assumed in this case.

 
Base Case Base Case w. Mn 5 Yr Avg prices Current Prices

IRR Pre-tax 29.4% 32.5% 32.7% 53.9%
IRR After tax 24.7% 27.5% 27.7% 46.0%
NPV* @ 0% $2,218 $3,297 $3,229 $6,388
NPV @ 6% $924 $1,345 $1,366 $2,913
NPV @ 8% $700 $1,020 $1,045 $2,313
NPV @ 10% $531 $777 $803 $1,860

*Note: all NPVs are after-tax


Sensitivities

The project is most sensitive to 4 key variables: copper price, cobalt price, capital costs, and operating costs. The sensitivity of the after-tax IRR and NPV (at 8% discount rate) relative to the Base Case (without manganese) are shown in the table below to indicate the effect of + or 10% changes in the key variables.

 
After Tax IRR NPV @ 8% ($Millions)

-10% Base Case +10% -10% Base Case +10%

Copper price 21.6% 24.7% 27.5% $571.5 $700.3 $821.5
Cobalt price 24.1% 24.7% 25.3% $662.9 $700.3 $737.7
Capital cost 27.3% 24.7% 22.3% $743.6 $700.3 $652.2
Operating cost 26.0% 24.7% 23.4% $765.2 $700.3 $635.4


Current Activity

Site Preparation

Environmental permit requirements to re-locate flora and fauna at several identified areas prior to construction are currently underway. Groundwater monitoring and baseline environmental data collection work is continuing. Geo-technical drilling and trenching is currently being conducted at the future sites of the process plant, the marine dock and tailings dam under the direction of Klohn Crippen Berger, Vancouver, B.C.

Financing

Strong support of the Boleo project has been shown by the financial community, including project finance lenders and metal off-take parties. Baja is working closely with its advisor, Endeavour Financial, which has prepared an Information Memorandum that will be distributed to the commercial bank market and other potential lenders immediately following release of the DFS Summary. Offers of bridge financing have also been received which will allow the Project development to go ahead without being delayed by the main financing process.

Endeavour Financial, the Company's financial advisor, commented: "The DFS confirms the robust economics of the Boleo Project and supports considerable debt capacity. There has been very strong interest in the Project from the commercial debt market and metal offtake sector, and we look forward to working with Baja in completing the financing of the project in the shortest timeframe possible."

Engineering and construction

Contracts are being finalized for basic engineering and construction. Wardrop Engineering in Vancouver, B.C., has commenced the set-up and basic engineering phase. It is expected that they will be supported by Bateman Engineering for Process Engineering and by a major construction company with experience in Mexico for constructability and pricing reviews during this phase.

Minor metals and Laboratory work

Work is continuing in investigation of low energy methods for production of manganese and zinc sulphate products. As well reviews are being conducted into the possible recovery of minor metals such as indium, gallium and germanium.

William Yeo, of Hellman and Schofield Pty. Ltd, a Qualified Person, has reviewed the Resource Model and the disclosure contained herein regarding the same and accepts responsibility for such disclosure. John Wyche, of Australian Mine Design and Development, a Qualified Person, has reviewed the surface mining reserves and the disclosure contained herein regarding the same and accepts responsibility for such disclosure. Tim Ross, of Agapito Associates Inc., a Qualified Person, has reviewed the underground mining reserves and the disclosure contained herein regarding the same and accepts responsibility for such disclosure. Michael Holmes, of Bateman Engineering, a Qualified Person, has reviewed the process plant discussion and the disclosure contained herein regarding the same and accepts responsibility for such disclosure.

We seek Safe Harbor.