Friday, September 20, 2024 2:31:32 PM
Friday, 20 September 2024
Constellation has signed a 20-year power purchase agreement with Microsoft that will see Three Mile Island unit 1 restarted, five years after it was shut down.
Three Mile Island unit 1 was shuttered in 2019 (Image: NRC/Exelon)
Constellation purchased the 837 MWe Three Mile Island Unit 1, in 1999. The unit, which had enough capacity to power 800,000 homes, was retired prematurely for economic reasons in 2019. In its last year of operation, the plant was producing electricity at maximum capacity 96.3% of the time - well above the industry average and employed more than 600 full-time workers.
The Unit 1 reactor is located adjacent to TMI Unit 2, which was shut down in 1979 after an accident which resulted in severe damage to the reactor core and is in the process of being decommissioned by its owner, Energy Solutions.
Constellation says "significant investments will be made to restore" unit 1 "including the turbine, generator, main power transformer and cooling and control systems. Restarting a nuclear reactor requires US Nuclear Regulatory Commission approval following a comprehensive safety and environmental review, as well as permits from relevant state and local agencies. Additionally, through a separate request, Constellation will pursue licence renewal that will extend plant operations to at least 2054".
The plant is to be renamed the Crane Clean Energy Centre - after Chris Cane, who was CEO of Constellation's parent company and passed away in April. The aim is for it to be online in 2028. Constellation says it aims to operate it for decades to come, and will create 3400 direct and indirect jobs and deliver more than USD3 billion in state and federal taxes
"This agreement is a major milestone in Microsoft's efforts to help decarbonise the grid in support of our commitment to become carbon negative. Microsoft continues to collaborate with energy providers to develop carbon-free energy sources to help meet the grids' capacity and reliability needs," said Bobby Hollis, vice president of energy, Microsoft.
Joe Dominguez, president and CEO, Constellation, said: "Powering industries critical to our nation’s global economic and technological competitiveness, including data centres, requires an abundance of energy that is carbon-free and reliable every hour of every day, and nuclear plants are the only energy sources that can consistently deliver on that promise. Before it was prematurely shuttered due to poor economics, this plant was among the safest and most reliable nuclear plants on the grid, and we look forward to bringing it back with a new name and a renewed mission to serve as an economic engine for Pennsylvania."
Governor Josh Shapiro said: "Under the careful watch of state and federal authorities, the Crane Clean Energy Center will safely utilise existing infrastructure to sustain and expand nuclear power in the Commonwealth while creating thousands of energy jobs and strengthening Pennsylvania’s legacy as a national energy leader."
Michael Goff, Acting Assistant Secretary, Department of Energy's Office of Nuclear Energy, said: "Always-on, carbon-free nuclear energy plays an important role in the fight against climate change and meeting the country's growing energy demands."
Friday's announcement could see the unit become the second in the USA - and the world - to return to operational status after being shut down for decommissioning. Holtec International is currently working to bring the Palisades single-unit pressurised water reactor in Michigan, which closed in 2022, bring back into service and is aiming to repower the plant by the end of 2025.
Earlier this year, the US Department of Energy Loan Programs Office conditionally committed up to USD1.52 billion for a loan guarantee to Holtec Palisades for the project, and in June US Energy Secretary Jennifer Granholm told Reuters she would be "surprised" if the office was not talking to other owners of shuttered plants about potential restarts.
Recent LTBR News
- Lightbridge President and CEO Seth Grae Interviewed Today on Schwab Network’s “Trading 360” • GlobeNewswire Inc. • 10/18/2024 04:36:54 PM
- Lightbridge to Hold Business Update & Third Quarter 2024 Earnings Conference Call on Friday, November 1st at 11 a.m. ET • GlobeNewswire Inc. • 10/17/2024 12:00:00 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 09/03/2024 04:07:26 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 09/03/2024 04:07:10 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 09/03/2024 04:06:53 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 08/09/2024 08:05:58 PM
- Form 424B3 - Prospectus [Rule 424(b)(3)] • Edgar (US Regulatory) • 08/09/2024 08:05:25 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 08/01/2024 09:00:42 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 08/01/2024 02:41:02 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 08/01/2024 02:40:48 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 08/01/2024 02:40:37 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 07/31/2024 09:00:25 PM
- Lightbridge Provides Business Update and Announces Second Quarter 2024 Financial Results • GlobeNewswire Inc. • 07/31/2024 08:05:00 PM
- Lightbridge to Hold Business Update & Second Quarter 2024 Earnings Conference Call on Thursday, August 1st at 4 p.m. ET • GlobeNewswire Inc. • 07/23/2024 12:00:00 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 07/19/2024 08:45:20 PM
- Lightbridge Welcomes Passage of the ADVANCE Act, Landmark Legislation to Expedite Commercial Deployment of Advanced Nuclear Fuel and Other Advanced Nuclear Technologies • GlobeNewswire Inc. • 06/25/2024 12:00:00 PM
- Form S-8 - Securities to be offered to employees in employee benefit plans • Edgar (US Regulatory) • 06/05/2024 08:30:44 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/04/2024 01:39:49 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/04/2024 01:39:02 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/04/2024 01:38:06 PM
- Lightbridge CEO Seth Grae Attends White House Summit on Domestic Nuclear Deployment • GlobeNewswire Inc. • 05/30/2024 12:00:00 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 05/10/2024 08:15:53 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 05/09/2024 09:00:27 PM
SANUWAVE Announces Reverse Stock Split, Note and Warrant Exchange, and PIPE Offering • SNWV • Oct 18, 2024 9:31 AM
Vocodia Addresses Recent Stock Price Movement and Future Strategic Partnerships • VHAI • Oct 18, 2024 9:00 AM
Mass Megawatts Announces the Start of an Online Discount Solar Energy Equipment Business with Revenue Recognized for the First Time Since Year 2010 in this Fiscal Quarter • MMMW • Oct 18, 2024 7:32 AM
Unitronix Corp Advances DeFi Innovation with Tokenized Real-World Assets Integration • UTRX • Oct 17, 2024 7:38 AM
Mass Megawatts Commences Solar Energy Sales Efforts • MMMW • Oct 16, 2024 7:45 AM
SANUWAVE Health Announces 1-For-375 Reverse Stock Split • SNWV • Oct 16, 2024 7:40 AM