Fertiglobe to take final investment decision on long-delayed 100MW Egyptian green hydrogen plant by July
Fertiliser producer remains coy on which electrolyser supplier is in line to replace original provider Plug Power
Polly Martin 1 May 2024

The Egypt Green hydrogen and ammonia project had originally been announced with promises that all 100MW of electrolysers would be installed in Ain Sokhna by the start of COP27 in Sharm El Sheikh, in November 2022, which would have made it the largest operational plant in the world at the time.
.....
One possible reason for the delay on FID for the full phase could be the decision by Egypt Green’s developers to drop the initial electrolyser supplier, Plug Power, in November 2022.

Fertiglobe has refused to comment on whether a new electrolyser provider has been identified for the project, nor which markets it plans to target with its green ammonia.

“Going to 100MW, there’s lot of other regulatory issues as well that you need to overcome,” Shata said at the conference, citing transmission of renewable energy from one side of the country to the other as one topic of discussion with government. “You need to finalise several other aspects to really get it in place.”
https://www.hydrogeninsight.com/industrial/fertiglobe-to-take-final-investment-decision-on-long-delayed-100mw-egyptian-green-hydrogen-plant-by-july/2-1-1635986