You are right Nebraskan some of the road work is due to NioCorp requirements.

Even if NioCorp's Road Construction stuff hasn't started yet, it's good to read.
sigh

Thanks

During the quarter ended December 31, 2023, the Company, through a contract engineering firm (Olsson), completed a 90% engineering package for various road improvements in the vicinity of the Elk Creek Project site, and shared the 90% engineering drawings with the Nebraska Department of Transportation and Johnson County as part of the normal process for approving the improvements.