a report released in April showed that nearly two-thirds of Colombia’s renewable energy projects due online in 2023 and 2024 are currently facing delays, largely due to growing political and regulatory risk concerns. The study, from the renewable energy association SER Colombia, revealed that just 28 of 80 projects are “advancing without problems.” Many have slowed due to complications in being granted environmental permits issued by licensing authority ANLA. New tax burdens, competition restrictions, and macroeconomic factors, including high interest rates and currency depreciation, have also created challenges.