WEEKLY DRILLING REPORT APRIL 21, 2023
WELL: Bayhanli-2

Progress: 562 meters
Measured Depth: 1058 metres
Week Summary:

Set 13 3/8” casing and cement
Prepare wellhead and BOP
Drill 12 ¼” x 13” hole to 1058 meters (measured depth)
Further Activities:
Continue to drill 12 ¼” x 13” hole to 2840 meters
Set 9 5/8” casing and cement
Drill 8 ½” hole to tatal depth of 3400 meters
Set 7” casing and cement
Perforate, test and turn over to production department