Lithium Chile

3h • 3 hours ago

Works progressing smoothly at our Arizaro Property in Argentina.
Phase 2 cleaning process is well underway and today the team started on a complimentary cleaning process - using a compressor working at its maximum range of operation.
This 'airlifting' was carried out at a depth of 300 metres in periods of 7 minutes to generate greater removal of solids.
Tomorrow we will begin the development of the well with a compressor by injecting air to ensure greater cleaning of the filters and the activation of the acquifers.
#lithium #lithiumchile #ontrack #argentina