Tonawanda Seneca Nation had challenged the findings of environmental impact study of hydrogen power plant at Genesee County industrial park
By Mark Scheer
A judge has rejected the Tonawanda Seneca Nation’s legal challenge to the findings of an environmental review of the planned construction of a $264 million hydrogen fuel plant in rural Genesee County.
In a Sept. 28 ruling, Genesee County Judge Charles Zambito determined that the nation failed to add the plant’s developer, Plug Power, as a “necessary party” in a lawsuit that sought to prevent the company from building its new plant near “sacred” hunting grounds on the nation’s territory in the Town of Alabama.
“The Nation is considering next steps in light of this decision,” said Gussie Lord, an attorney with the group Earthjustice, the nonprofit environmental law firm that assisted the Tonawanda Seneca Nation in filing its legal claim.
Plug Power, an Albany company that specializes in the development of hydrogen fuel cell systems, announced in May plans to build the new “green hydrogen” plant at the Science, Technology and Advanced Manufacturing Park, a 1,250-acre industrial site that is being developed near the edge of the Nation’s territory in Genesee County.
The nation filed an initial lawsuit on June 4, naming the Genesee County Economic Development Agency as the lone defendant and challenging the agency’s finding that “all potential impacts” associated with the project had been “adequately addressed.” On June 18, the Nation filed an amended motion to add as defendants officers of Plug Power and the Genesee County Economic Development Agency.
In both legal filings, leaders from the Nation argued that the project had the potential to infringe upon “property of religious and cultural significance” on the nation’s territory, including the “Big Woods,” a dense forest area near the western edge of the STAMP site.
In his ruling, Zambito determined that the nation filed its initial lawsuit within the four-month window allowed for objecting to the findings of environmental reviews. However, he also determined that the nation’s amended filing failed to add Plug Power as a respondent in a timely fashion and ruled the company was a “necessary party” to allow the nation’s lawsuit to move forward.
Officials with the Genesee County Economic Development Center have spent $26 million in mostly state funds on land acquisition, design, engineering and other “soft” costs at STAMP. Plug Power is scheduled to become the first commercial tenant at the site and has agreed to build a $55 million substation that would provide electricity to its plant as well as future STAMP tenants.
In exchange for creating 68 full-time jobs at the hydrogen fuel facility, Plug Power will receive tax breaks and power discounts totaling $270 million, representing a subsidy equal to more than $4 million per job.
Recent PLUG News
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/07/2024 08:34:17 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/07/2024 08:33:01 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/07/2024 08:32:32 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/07/2024 08:31:53 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/07/2024 08:31:01 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 06/07/2024 08:30:33 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 06/07/2024 01:00:18 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 06/05/2024 01:00:29 PM
- Plug to Webcast Annual Shareholder Meeting on June 5, 2024 • GlobeNewswire Inc. • 05/30/2024 09:55:00 PM
- Form 8-K - Current report • Edgar (US Regulatory) • 05/24/2024 08:40:29 PM
- Form 424B7 - Prospectus [Rule 424(b)(7)] • Edgar (US Regulatory) • 05/24/2024 08:02:55 PM
- Plug, Airbus, Delta, Hartsfield-Jackson Atlanta International Airport Study Feasibility of Hydrogen Hub at World’s Busiest Airport • GlobeNewswire Inc. • 05/21/2024 03:31:00 PM
- Shareholders that lost money on Plug Power Inc.(PLUG) should contact The Gross Law Firm about pending Class Action - PLUG • PR Newswire (US) • 05/21/2024 09:45:00 AM
- Plug Signs 3 GW BEDP Contract with Allied Green Ammonia for Electrolyzer Project in Australia • GlobeNewswire Inc. • 05/16/2024 11:00:00 AM
- Plug to Revolutionize Middle-Mile Delivery with Class 6 Fuel Cell Electric Truck Integration • GlobeNewswire Inc. • 05/15/2024 11:00:00 AM
- Form 8-K - Current report • Edgar (US Regulatory) • 05/14/2024 12:06:42 PM
- Plug Receives $1.66 Billion Conditional Commitment Loan Guarantee From Department of Energy for Green Hydrogen Development Pipeline • GlobeNewswire Inc. • 05/14/2024 12:00:00 PM
- Investors who lost money on Plug Power Inc.(PLUG) should contact The Gross Law Firm about pending Class Action - PLUG • PR Newswire (US) • 05/14/2024 09:45:00 AM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 05/13/2024 08:34:02 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 05/13/2024 08:33:19 PM
- Form 4 - Statement of changes in beneficial ownership of securities • Edgar (US Regulatory) • 05/13/2024 08:30:53 PM
- Form 10-Q - Quarterly report [Sections 13 or 15(d)] • Edgar (US Regulatory) • 05/09/2024 08:02:15 PM
- U.S. Index Futures Dip, Bank of England Holds Interest Rates at 5.25% • IH Market News • 05/09/2024 11:47:20 AM
- Form 8-K - Current report • Edgar (US Regulatory) • 05/09/2024 11:22:17 AM
- Plug Announces First Quarter 2024 Financial Results • GlobeNewswire Inc. • 05/09/2024 11:00:00 AM
North Bay Resources Announces Composite Assays of 0.53 and 0.44 Troy Ounces per Ton Gold in Trenches B + C at Fran Gold, British Columbia • NBRI • Jun 18, 2024 9:18 AM
VAYK Assembling New Management Team for $64 Billion Domestic Market • VAYK • Jun 18, 2024 9:00 AM
Fifty 1 Labs, Inc Announces Acquisition of Drago Knives, LLC • CAFI • Jun 18, 2024 8:45 AM
Hydromer Announces Attainment of ISO 13485 Certification • HYDI • Jun 17, 2024 9:22 AM
ECGI Holdings Announces LOI to Acquire Pacific Saddlery to Capitalize on $12.72 Billion Market Potential • ECGI • Jun 13, 2024 9:50 AM
Fifty 1 Labs, Inc. Announces Major Strategic Advancements and Shareholder Updates • CAFI • Jun 13, 2024 8:45 AM