2 updates in 1 week.??
Testing while being installed, was on point!

As noted in yesterday’s update, the equipment arrived at the demonstration site on Tuesday, June 16th. Our pipeline partner installed the grid pack and blind flange assembly this afternoon, June 18th, overseen by Christopher Gallagher and Shannon Rasmussen of QS Energy. During the assembly and pre-installation procedure, our engineers conducted a series of high voltage impedance tests to verify both electrical continuity and the impedance of the assembled grid pack and blind flange. These tests showed that the system continues to test at high levels of impedance indicating the new insulating materials are performing as expected, consistent with earlier tests on the newly modified design described in the June 17, 2020 update.