April 22, 2020

Work on the construction of utilities has started

?

Enexis started this week with the construction of a 700m long gas pipe to eventually connect the gas production of the digester to the public net work.
The pipeline largely runs on its own grounds at the rear of the plot and will be connected to the Enexis pipeline network, which runs parallel to the track.

thanks for updating M

In addition, Enexis will start installing a new electrical cable for the digester in week 20/2020. This will be constructed from the transformer space past the village house on the Valentine in Sterksel, to the grounds of Poort 43.

Due to the measures surrounding COVID-19, it is still unclear when construction can resume.
Of course we are working hard on this and the discussions with the assembly company to deploy double assembly capacity are going well.