InvestorsHub Logo
Followers 1
Posts 142
Boards Moderated 0
Alias Born 10/26/2017

Re: None

Wednesday, 02/12/2020 8:37:17 PM

Wednesday, February 12, 2020 8:37:17 PM

Post# of 12822
Didn't quite copy/paste well, but it looks pretty damn solid to me.

Petitioner Poly Met Mining, Inc. respectfully submits this Petition for Review:
I. Legal issues and their disposition by the court of appeals
Does Minnesota Statutes section ??.??? mandate a contested case hearing
whenever an agency faces conflicting evidence, regardless of whether substantial
evidence supports its factual findings?
The court of appeals’ published opinion interpreted the relevant statute to
require a contested case hearing whenever “there is probative, competent, and
conflicting evidence on a material fact issue.” (A.??.) That reading disregards the
statute’s operative language, this Court’s application of virtually identical language,
and the Minnesota Administrative Procedure Act’s deferential standard of review.
II. Criteria relied on to support the petition
Review is appropriate under Rule of Civil Appellate Procedure ???, subdivision
?(a), (c), and (d).
This case presents important questions that transcend the interests of the
parties. The statute at issue uses the same contested case hearing criteria as the
Minnesota Pollution Control Agency, which permits thousands of projects every
year without holding contested case hearings. So if the decision below stands,
permitting and environmental review throughout the state will become less
predictable and more burdensome as agency findings supported by substantial
evidence are relitigated before administrative law judges.
2
III. Statement of the case
To obtain its permit to mine and dam safety permits, PolyMet navigated the
most comprehensive environmental review and permitting process in Minnesota
history. As the court of appeals recognized, that process began in ????, when the
Department of Natural Resources and U.S. Army Corps of Engineers began scoping
a joint Environmental Impact Statement. More than ten years later, having
published both draft and supplemental draft statements, the agencies released their
Final Environmental Impact Statement. When DNR found the Final EIS adequate in
March ????, no one challenged its determination.
Later that year, PolyMet submitted both a ?,???-page permit to mine
application that covered every aspect of PolyMet’s mine plan and two comparably
thorough dam safety permit applications. DNR and its outside consultants then
spent over a year with PolyMet gathering more information and improving the
applications. That led PolyMet to file the revised applications that were ultimately
incorporated into DNR’s draft permits.
DNR noticed a ??-day public comment period on its draft permit to mine.
During that time, it received thousands of comments and two contested case
hearing petitions.1
The agency spent the next eight months evaluating the materials
it had received. In November ????, it issued PolyMet a permit to mine, together with
a ???-page document titled “Findings of Fact, Conclusions, and Order of
Commissioner.” Relying on the Final EIS and extensive factual findings, including
?? pages devoted specifically to the contested case hearing petitions, DNR
concluded that “there was not a reasonable basis underlying a disputed material
1
DNR followed a similar process for the dam safety permits, but it did not receive
any petitions for a contested case hearing.
3
issue of fact” and that a contested case hearing would not introduce information
that would “aid the commissioner in resolving any disputed facts.”2
On those
grounds, it denied the petitions.
Relators filed certiorari petitions challenging DNR’s permitting decisions on
numerous grounds. The court of appeals held that DNR had misinterpreted the
relevant statute, reversed DNR’s permitting decisions, and instructed DNR to hold
a contested case hearing. (A.??)
IV. Brief argument in support of the petition
The court of appeals’ holding in this case reshapes the place of contested case
hearings in project permitting, raising questions of statewide importance that are
bound to recur regularly.
A. As an initial matter, the court of appeals’ interpretation of the
contested case criteria departs from the relevant statute’s plain language and this
Court’s decisions. Far from of “[s]ynthesizing” precedent, as it claimed, the court of
appeals subordinated this Court’s most relevant decisions in a way that should not
be applied statewide without this Court’s consideration.
Under section ??.???, subdivision ?, a contested case hearing “must” be held
“if the commissioner finds that”:
(?) there is a material issue of fact in dispute concerning the
completed application before the commissioner;
(?)the commissioner has jurisdiction to make a determination
on the disputed material issue of fact; and
2 See xxxx
4
(?)there is a reasonable basis underlying a disputed material
issue of fact so that a contested case hearing would allow the
introduction of information that would aid the commissioner in
resolving the disputed facts in order to make a final decision on
the completed application.
As a matter of statutory interpretation, the court of appeals reasoned that the phrase
“so that” in the third contested case criterion reflected a “legislative judgment that
a contested-case hearing will be helpful in cases where there are genuine, material
disputes of fact.” (A.??–??.) That reading is wrong for at least two reasons.
?. The first contested case criterion requires “a material issue of fact in
dispute.” Minn. Stat. § ??.???, subd. ?(a)(?). The third criterion—the one the court
of appeals was interpreting—requires more. It requires “a reasonable basis
underlying a disputed material issue of fact.” Id., subd. ?(a)(?) (emphasis added). By
holding that “a contested-case hearing will be helpful in cases where there are
genuine, material disputes of fact,” the court of appeals’ decision renders the third
criterion superfluous. In Minnesota, “[a] statute should be interpreted, whenever
possible, to give effect to all of its provisions; no word, phrase, or sentence should
be deemed superfluous, void, or insignificant.” Am. Family Ins. Group v. Schroedl,
??? N.W.?d ???, ??? (Minn. ????) (citation and internal quotation marks omitted).
?. The court of appeals’ reading of the statute ignores the operative phrase
that applies to all three contested case criteria: “if the commissioner finds that.” The
decision below essentially nullified that limiting language, substituting the court of
appeals’ judgment for the commissioner’s. Under the Minnesota Administrative
Procedure Act, courts uphold agency factual findings unless they are “unsupported
by substantial evidence” or “arbitrary or capricious.” Minn. Stat. § ??.??. Here, DNR
made extensive factual findings, supported by substantial evidence, related to the
5
contested case hearing criteria. By instead focusing solely on whether disappointed
participants had presented a conflicting case, the court of appeals committed an
error of both statutory interpretation and administrative law.
What is more, the court of appeals’ new rule requiring contested case hearings
any time project opponents offer “probative, competent, and conflicting evidence
on a material fact issue” contradicts this Court’s precedent. Indeed, this Court in
Northern States Power Co., ??? N.W.?d ??? (Minn. ????), reversed a decision much
like the one in this case. There, the court below had ordered a contested case hearing
based on the existence of “genuine issues of material fact” supported by proffered
experts, proposed findings, and alleged new facts. Request for Permit Regarding the
Proposed N. States Power Co. Indus. Wasted Incinerator, ???? WL ?????, at *?
(Minn. Ct. App. ????). This Court held that was not enough. After “review of the
extensive record,” the Court explained that “the agency decision was supported by
the requisite substantial evidence” and that relators were not “entitle[d] to a
contested case hearing.” N. States Power, ??? N.W.?d at ???. Similarly, the Court in
Amendment No. ? to Air Emission Facility Permit No. ???I-??-OT-?, ??? N.W.?d ???,
???-?? (Minn. ????), reversed a court of appeals decision that had ordered a
contested case because “evidence . . . exist[ed] on material questions raised.” The
court below effectively rejected Northern States Power and Amendment No. ?,
instead adopting the reasoning of the decisions they overturned.
B. The court of appeals’ new contested case hearing requirement will alter
the environmental review and permitting process at DNR and PCA. In principle, the
Minnesota Environmental Policy Act frontloads environmental review, ensuring
that decisionmakers and the public “understand[] the impact which a proposed
6
project will have on the environment” before that project is permitted. Minn.
R. ????.????, subp. ?. To that end, the approval process for many projects—
including any project with “the potential for significant environmental effects”—
begins with an Environmental Impact Statement. Minn. R. ????.????, subp. ?(A).
PolyMet’s project spent approximately ?? years in that process, which included
multiple rounds of public review and comment.
When opponents of PolyMet’s project petitioned for a contested case hearing,
DNR relied in large part on findings from its decade of unchallenged environmental
review to conclude that the petitioners’ factual claims lacked a “reasonable basis” so
that a contested case hearing would not “aid the commissioner” in making a final
decision. The court of appeals disagreed, but not because DNR’s findings were
unsupported by substantial evidence. It held, as a matter of law, that petitioners are
entitled to a contested case hearing any time they present “probative, competent,
and conflicting evidence on a material fact issue.” (A.??.) This Court has purposely
stopped well short of that approach, choosing instead to place appropriate weight
on findings made by specialized agencies based on substantial evidence gathered
during environmental review. N. States Power, ??? N.W.?d at ???; Amendment
No. ?, ??? N.W.?d at ???.
The court of appeals’ contrary holding upsets the balance of Minnesota’s
environmental review and permitting process. Instead of encouraging agencies to
rely on independent studies conducted over the course of many months or years—
an EIS—the court of appeals’ decision allows essentially any factual dispute to be
carried into a contested case hearing at the end of the permitting process.
7
This change hurts PolyMet, which acquired its permits after the most
elaborate environmental review and permitting process in Minnesota history, only
to have the court of appeals decide that a contested case hearing was required all
along. And because the statute at issue in this case applies to all permits to mine,
every future mining project faces the same conundrum: Years of environmental
review can now be disputed in a contested case hearing based simply on “probative,
competent, and conflicting evidence.” Such hearings add time and legal uncertainty
that did not exist before the court of appeals’ decision.
The court of appeals’ decision similarly affects projects permitted by PCA,
which uses nearly identical contested case hearing criteria. See Minn. R. ????.????,
subp. ?. As documented in its annual permitting efficiency report, PCA receives
dozens of individualized permit applications each year for projects that require new
construction.3
It almost never holds a contested case hearing, possibly because the
Legislature has set a goal that even the most complex permits should be issued or
denied within ??? days
. Minn. Stat. § ???.??, subd. ?b(a). Absent this Court’s review,
all of these projects will now be susceptible to a contested case hearing based on
“probative, competent, and conflicting evidence.” That includes more than just the
industries that must comply with PCA’s strict air and water quality requirements.
PCA permits everything from family-owned businesses to municipal wastewater
treatment facilities.
If the court of appeals’ decision stands, everyone regulated by
PCA faces a longer, more uncertain permitting and contested case hearing process.

Volume:
Day Range:
Bid:
Ask:
Last Trade Time:
Total Trades:
  • 1D
  • 1M
  • 3M
  • 6M
  • 1Y
  • 5Y
Recent PLM News