1) Engineering design and construction drawings for zoning and construction permits: 4-9 months depending on complexity of design and number of rounds required to resolve customer comments (PR July 2019 stated that design work was just completing and they had selected a firm to do the detailed design).
2) Permit approvals 1-6 months: depends on review period requirements and how well the engineering firm meets code requirements without having to resolve multiple rounds of comments from government agency issuing the permits.
They should at this point 6 months later be close to having permits to start construction on the best design/build construction schedule.
Register for free to join our community of investors and share your ideas. You will also get access to streaming quotes, interactive charts, trades, portfolio, live options flow and more tools.