Goro +.19 to $3.41

Adding about 2k oz/month. Goro previously did 27K for 2018 in just gold so at least doubled gold production from here on out. New mine expected to reach 40K/yr. Relatively short life at 6 years so need additional exploration or deposits. Goro is already profitable so should get nice boost from this doubling+ of gold production.

COLORADO SPRINGS, CO, Oct. 07, 2019 (GLOBE NEWSWIRE) -- via NEWMEDIAWIRE – Gold Resource Corporation (NYSE American: GORO) (the “Company”) today announced its Isabella Pearl gold mine, located in Mineral County, Nevada, has reached commercial production levels. This commercial production announcement is based on mining rates, ore placement on the heap leach pad, mining and process costs, production ramp-up, and reaching positive operational cash flow during the month of September. The Company produced first gold dore from the project in late April 2019 and expects additional improvements as the project continues through the ramp up phase. Gold Resource Corporation is a gold and silver producer, developer and explorer with operations in Oaxaca, Mexico and Nevada, USA. The Company has returned $112 million to its shareholders in consecutive monthly dividends since July 2010 and offers its shareholders the option to convert their cash dividends into physical gold and silver and take delivery.

Gold production levels at the Isabella Pearl mine have been ramping up since the first dore bar was produced in late April 2019. Preliminary September production of gold loaded to carbon and dore produced totaled in excess of 2,000 ounces. The Company plans to update its 2019 global gold production outlook in the upcoming third quarter preliminary production announcement to include estimated gold ounces targeted from its Isabella Pearl project for the fourth quarter. While it is still early in the project ramp up phase, 2,000 ounces of monthly gold production at Isabella Pearl is expected to continue generating positive cash flow by covering operational costs at the project assuming a gold price of $1,450 per ounce. The Company’s 2020 annual production outlook for both Oaxaca, Mexico and Nevada, U.S.A. will be released in early 2020.

Construction of the Isabella Pearl project’s ADR process facility is complete with final commissioning occurring over the next several weeks to enable on-site dore production. Off-site processing of the gold infused carbon into dore will continue until the on-site dore facility is fully optimized.

Mr. Jason Reid, CEO and President of Gold Resource Corporation, stated, “I am very pleased to report the Isabella Pearl mine, which broke ground and produced first dore in just ten months, has reached commercial production levels just sixteen months after breaking ground on the project in June 2018. Our team has worked extremely hard these past few months navigating the challenges of mine commissioning, managing construction contractor difficulties and the typical production ramp up of a new mine. I am very excited that during the month of September the Isabella Pearl mine moved into a phase where mining and processing rates and ore placement are now expected to generate positive cash flow on a consistent basis. This is a milestone for any mining project and should have a significant impact on the Company’s overall revenues and net income moving forward.”

The Isabella Pearl ramp up phase will continue over the next year as the deposit is made up of two primary ore bearing areas, the Isabella and the Pearl with the former mineralization outcropping at the surface and the latter higher-grade mineralization located deeper within the deposit. Approximately eighty percent of the ore in this deposit is in the Pearl structure, and the Company continues removing overburden to reach this high-grade area targeted in 2020.

Mr. Reid stated, “There will most likely be unforeseen additional challenges as there always are in the mining industry, but given where we were sixteen months ago putting the first shovel in the ground to where we are today, loading the pad with Isabella ore and having reached positive cash flow in September, I am very pleased and excited at our progress at the Isabella Pearl mine. With this positive cash flow development, I believe we are very close to reaching the inflection point of a near-term shareholder dividend increase.”

Mr. Reid continued, “The “at-the-market” ATM facility used to help finance the project’s completion is still in place and is expected to remain in place going forward as optionality for the Company if and when needed. I am pleased to report the Company has not used the ATM since July 30, 2019. While the Company reserves the right to further utilize the ATM, we currently do not foresee the need to do so.”

Please post stock symbols first in all your posts. If it's a foreign stock, please list the US pk equivalent symbol.

If the Commodities Boom is Over, I am just a Gold Bug headed for the Windshield of LIFE

Join the InvestorsHub Community

Register for free to join our community of investors and share your ideas. You will also get access to streaming quotes, interactive charts, trades, portfolio, live options flow and more tools.