NYISO Queue status. 7.4MW already in PPA because it did not need an interconnection. These 2 remain in the Queue with PPAs pending any day and $100 million funding already in place for them from Generate Capital.
649 CR Fuel Cell, LLC Clare Rose 8/3/17 13.9 13.9 FC Suffolk, NY K William Floyd Substation 69kV LIPA 5 11/30/18 FES
650 BRT Fuel Cell, LLC Brookhaven Rail Terminal 8/3/17 18.5 18.5 FC Suffolk, NY K W. Yaphank - Yaphank 69kV LIPA 5 11/30/18 FES