Summary of estimated completion dates: Timeline Summary See below for a summary of the estimated timeline for the completion of Phase 1: Base Building: Completed. Health Canada Attestation Video: February 7 and 8, 2019. Building Occupancy: February 28, 2019. Flowering Rooms 1 and 2 (Partial): March 15, 2019. Cultivation License: Expected Q1, 2019. Flowering Rooms 3 8: December 31, 2019. This timeline is subject to change and is based on current internal estimates.