"The Army Corp's 408 program office stopped work on the 408 permit for the project in February 2018 on the
basis that a fee agreement with the company was needed to continue working. The fee agreement was never
produced by the Corps, and the Corps did not complete any additional work on the 408 permit. This was a
partial driver in the Company's decision to remove from the project's design those features of the project that
triggered the 408 permit.
"

From the Senate Testimony as I mentioned. Bottom of page 12.

https://www.energy.senate.gov/public/index.cfm/files/serve?File_id=D288D38C-5223-4BAC-9626-E4A9C4CFF982