Tuesday, October 30, 2018 10:31:30 PM
"The Company has delayed ground breaking ceremony as cost estimate to build phase 1 came in far in
excess of preliminary budget. The Company along with EPC made the decision to defer some of the
scope of phase 1 into phase 2. Two of the major suppliers have been asked to resubmit budget using
new scope. We have heard back from one with a price reduction of approximately $15 million. We expect
to have second number in next couple of weeks which will allow us to proceed with current funding."
Avant Technologies Equipping AI-Managed Data Center with High Performance Computing Systems • AVAI • May 10, 2024 8:00 AM
VAYK Discloses Strategic Conversation on Potential Acquisition of $4 Million Home Service Business • VAYK • May 9, 2024 9:00 AM
Bantec's Howco Awarded $4.19 Million Dollar U.S. Department of Defense Contract • BANT • May 8, 2024 10:00 AM
Element79 Gold Corp Successfully Closes Maverick Springs Option Agreement • ELEM • May 8, 2024 9:05 AM
Kona Gold Beverages, Inc. Achieves April Revenues Exceeding $586,000 • KGKG • May 8, 2024 8:30 AM
Epazz plans to spin off Galaxy Batteries Inc. • EPAZ • May 8, 2024 7:05 AM