Most importantly, at the construction coalface we saw activities ramp up significantly to hit peak levels by Quarter-end, with more than 650 people expected to be on site through the February-May period and multiple work-fronts advancing in parallel to ensure that we meet our target of starting commissioning of the plant during the June quarter and commencing product shipments by mid-2018.

The next few months will be a pivotal time for Pilbara as construction enters its final and most important stage, open pit mining ramps up, DSO sales commence early next quarter and we prepare to start the all- important plant commissioning process.”