From an industrial project resource i use for work ::::::


Plant Owner XpressWest Plant Parent XpressWest
Plant Name Las Vegas Station



Project Probability Medium (70-80%)
Scope XpressWest and Nevada High Speed Rail Authority (Owner/JV) with Marnell Companies (Consultant) performs Project Scope for a High Speed Rail Line Phase I and II. DETAILS: Construct 185-mile Double Electric Track from Victorville, California to Las Vegas adjacent to I-15 plus Construct 60-miles from Victorville to Palmdale, California on Electric Unit Trains to Increase Ridership and to Reduce Major Pollutants by 40%. REQUIRES: Tracks, Trains, Demolition, Excavation, Foundations, Tracks, Ballast, Ties, Turn-Outs, Switches, Switchgears, Stations, Underground Conduit, Duct Banks, Communications & Signal System, Lighting, MCC plus Controls (PLC). ENVIRONMENTAL: (L) Drainage, Containment.
Schedule XpressWest and Nevada High Speed Rail Authority with Marnell Companies continues with Project Scope through 2Q18 (Apr). XpressWest and Nevada High Speed Rail Authority reviews and selects General Contractor 3Q18 (May). General Contractor releases Equipment RFQ's and Bid Documents plus reviews and selects Subcontractors as needed 3Q18 (Sep)-2Q20. Expected Construction Kick-Off 4Q18 (Oct). Project Completion 4Q24 (Dec).

Project Milestones
AFE: 201807 Sub Bid Doc: 201809 Completion: 31-Dec-2024 Precision: QUARTER
Equip RFQ: 201809 Kick-Off: 201812 Kickoff Slippage: 20 Months Construction Duration: 73 Months